42 USC CHAPTER 85, SUBCHAPTER I, Part D: Plan Requirements for Nonattainment Areas
Result 1 of 1
   
 
42 USC CHAPTER 85, SUBCHAPTER I, Part D: Plan Requirements for Nonattainment Areas
From Title 42—THE PUBLIC HEALTH AND WELFARECHAPTER 85—AIR POLLUTION PREVENTION AND CONTROLSUBCHAPTER I—PROGRAMS AND ACTIVITIES

Part D—Plan Requirements for Nonattainment Areas

subpart 1—nonattainment areas in general

§7501. Definitions

For the purpose of this part—

(1) Reasonable further progress.—The term "reasonable further progress" means such annual incremental reductions in emissions of the relevant air pollutant as are required by this part or may reasonably be required by the Administrator for the purpose of ensuring attainment of the applicable national ambient air quality standard by the applicable date.

(2) Nonattainment area.—The term "nonattainment area" means, for any air pollutant, an area which is designated "nonattainment" with respect to that pollutant within the meaning of section 7407(d) of this title.

(3) The term "lowest achievable emission rate" means for any source, that rate of emissions which reflects—

(A) the most stringent emission limitation which is contained in the implementation plan of any State for such class or category of source, unless the owner or operator of the proposed source demonstrates that such limitations are not achievable, or

(B) the most stringent emission limitation which is achieved in practice by such class or category of source, whichever is more stringent.


In no event shall the application of this term permit a proposed new or modified source to emit any pollutant in excess of the amount allowable under applicable new source standards of performance.

(4) The terms "modifications" and "modified" mean the same as the term "modification" as used in section 7411(a)(4) of this title.

(July 14, 1955, ch. 360, title I, §171, as added Pub. L. 95–95, title I, §129(b), Aug. 7, 1977, 91 Stat. 745; amended Pub. L. 101–549, title I, §102(a)(2), Nov. 15, 1990, 104 Stat. 2412.)


Editorial Notes

Amendments

1990Pub. L. 101–549, §102(a)(2)(A), struck out "and section 7410(a)(2)(I) of this title" after "purpose of this part".

Pars. (1), (2). Pub. L. 101–549, §102(a)(2)(B), (C), amended pars. (1) and (2) generally. Prior to amendment, pars. (1) and (2) read as follows:

"(1) The term 'reasonable further progress' means annual incremental reductions in emissions of the applicable air pollutant (including substantial reductions in the early years following approval or promulgation of plan provisions under this part and section 7410(a)(2)(I) of this title and regular reductions thereafter) which are sufficient in the judgment of the Administrator, to provide for attainment of the applicable national ambient air quality standard by the date required in section 7502(a) of this title.

"(2) The term 'nonattainment area' means, for any air pollutant an area which is shown by monitored data or which is calculated by air quality modeling (or other methods determined by the Administrator to be reliable) to exceed any national ambient air quality standard for such pollutant. Such term includes any area identified under subparagraphs (A) through (C) of section 7407(d)(1) of this title."


Statutory Notes and Related Subsidiaries

Effective Date

Part effective Aug. 7, 1977, except as otherwise expressly provided, see section 406(d) of Pub. L. 95–95, set out as an Effective Date of 1977 Amendment note under section 7401 of this title.

§7502. Nonattainment plan provisions in general

(a) Classifications and attainment dates

(1) Classifications

(A) On or after the date the Administrator promulgates the designation of an area as a nonattainment area pursuant to section 7407(d) of this title with respect to any national ambient air quality standard (or any revised standard, including a revision of any standard in effect on November 15, 1990), the Administrator may classify the area for the purpose of applying an attainment date pursuant to paragraph (2), and for other purposes. In determining the appropriate classification, if any, for a nonattainment area, the Administrator may consider such factors as the severity of nonattainment in such area and the availability and feasibility of the pollution control measures that the Administrator believes may be necessary to provide for attainment of such standard in such area.

(B) The Administrator shall publish a notice in the Federal Register announcing each classification under subparagraph (A), except the Administrator shall provide an opportunity for at least 30 days for written comment. Such classification shall not be subject to the provisions of sections 553 through 557 of title 5 (concerning notice and comment) and shall not be subject to judicial review until the Administrator takes final action under subsection (k) or (l) of section 7410 of this title (concerning action on plan submissions) or section 7509 of this title (concerning sanctions) with respect to any plan submissions required by virtue of such classification.

(C) This paragraph shall not apply with respect to nonattainment areas for which classifications are specifically provided under other provisions of this part.

(2) Attainment dates for nonattainment areas

(A) The attainment date for an area designated nonattainment with respect to a national primary ambient air quality standard shall be the date by which attainment can be achieved as expeditiously as practicable, but no later than 5 years from the date such area was designated nonattainment under section 7407(d) of this title, except that the Administrator may extend the attainment date to the extent the Administrator determines appropriate, for a period no greater than 10 years from the date of designation as nonattainment, considering the severity of nonattainment and the availability and feasibility of pollution control measures.

(B) The attainment date for an area designated nonattainment with respect to a secondary national ambient air quality standard shall be the date by which attainment can be achieved as expeditiously as practicable after the date such area was designated nonattainment under section 7407(d) of this title.

(C) Upon application by any State, the Administrator may extend for 1 additional year (hereinafter referred to as the "Extension Year") the attainment date determined by the Administrator under subparagraph (A) or (B) if—

(i) the State has complied with all requirements and commitments pertaining to the area in the applicable implementation plan, and

(ii) in accordance with guidance published by the Administrator, no more than a minimal number of exceedances of the relevant national ambient air quality standard has occurred in the area in the year preceding the Extension Year.


No more than 2 one-year extensions may be issued under this subparagraph for a single nonattainment area.

(D) This paragraph shall not apply with respect to nonattainment areas for which attainment dates are specifically provided under other provisions of this part.

(b) Schedule for plan submissions

At the time the Administrator promulgates the designation of an area as nonattainment with respect to a national ambient air quality standard under section 7407(d) of this title, the Administrator shall establish a schedule according to which the State containing such area shall submit a plan or plan revision (including the plan items) meeting the applicable requirements of subsection (c) and section 7410(a)(2) of this title. Such schedule shall at a minimum, include a date or dates, extending no later than 3 years from the date of the nonattainment designation, for the submission of a plan or plan revision (including the plan items) meeting the applicable requirements of subsection (c) and section 7410(a)(2) of this title.

(c) Nonattainment plan provisions

The plan provisions (including plan items) required to be submitted under this part shall comply with each of the following:

(1) In general

Such plan provisions shall provide for the implementation of all reasonably available control measures as expeditiously as practicable (including such reductions in emissions from existing sources in the area as may be obtained through the adoption, at a minimum, of reasonably available control technology) and shall provide for attainment of the national primary ambient air quality standards.

(2) RFP

Such plan provisions shall require reasonable further progress.

(3) Inventory

Such plan provisions shall include a comprehensive, accurate, current inventory of actual emissions from all sources of the relevant pollutant or pollutants in such area, including such periodic revisions as the Administrator may determine necessary to assure that the requirements of this part are met.

(4) Identification and quantification

Such plan provisions shall expressly identify and quantify the emissions, if any, of any such pollutant or pollutants which will be allowed, in accordance with section 7503(a)(1)(B) of this title, from the construction and operation of major new or modified stationary sources in each such area. The plan shall demonstrate to the satisfaction of the Administrator that the emissions quantified for this purpose will be consistent with the achievement of reasonable further progress and will not interfere with attainment of the applicable national ambient air quality standard by the applicable attainment date.

(5) Permits for new and modified major stationary sources

Such plan provisions shall require permits for the construction and operation of new or modified major stationary sources anywhere in the nonattainment area, in accordance with section 7503 of this title.

(6) Other measures

Such plan provisions shall include enforceable emission limitations, and such other control measures, means or techniques (including economic incentives such as fees, marketable permits, and auctions of emission rights), as well as schedules and timetables for compliance, as may be necessary or appropriate to provide for attainment of such standard in such area by the applicable attainment date specified in this part.

(7) Compliance with section 7410(a)(2)

Such plan provisions shall also meet the applicable provisions of section 7410(a)(2) of this title.

(8) Equivalent techniques

Upon application by any State, the Administrator may allow the use of equivalent modeling, emission inventory, and planning procedures, unless the Administrator determines that the proposed techniques are, in the aggregate, less effective than the methods specified by the Administrator.

(9) Contingency measures

Such plan shall provide for the implementation of specific measures to be undertaken if the area fails to make reasonable further progress, or to attain the national primary ambient air quality standard by the attainment date applicable under this part. Such measures shall be included in the plan revision as contingency measures to take effect in any such case without further action by the State or the Administrator.

(d) Plan revisions required in response to finding of plan inadequacy

Any plan revision for a nonattainment area which is required to be submitted in response to a finding by the Administrator pursuant to section 7410(k)(5) of this title (relating to calls for plan revisions) must correct the plan deficiency (or deficiencies) specified by the Administrator and meet all other applicable plan requirements of section 7410 of this title and this part. The Administrator may reasonably adjust the dates otherwise applicable under such requirements to such revision (except for attainment dates that have not yet elapsed), to the extent necessary to achieve a consistent application of such requirements. In order to facilitate submittal by the States of adequate and approvable plans consistent with the applicable requirements of this chapter, the Administrator shall, as appropriate and from time to time, issue written guidelines, interpretations, and information to the States which shall be available to the public, taking into consideration any such guidelines, interpretations, or information provided before November 15, 1990.

(e) Future modification of standard

If the Administrator relaxes a national primary ambient air quality standard after November 15, 1990, the Administrator shall, within 12 months after the relaxation, promulgate requirements applicable to all areas which have not attained that standard as of the date of such relaxation. Such requirements shall provide for controls which are not less stringent than the controls applicable to areas designated nonattainment before such relaxation.

(July 14, 1955, ch. 360, title I, §172, as added Pub. L. 95–95, title I, §129(b), Aug. 7, 1977, 91 Stat. 746; amended Pub. L. 95–190, §14(a)(55), (56), Nov. 16, 1977, 91 Stat. 1402; Pub. L. 101–549, title I, §102(b), Nov. 15, 1990, 104 Stat. 2412.)


Editorial Notes

Amendments

1990Pub. L. 101–549 amended section generally, substituting present provisions for provisions which related to: in subsec. (a), expeditious attainment of national ambient air quality standards; in subsec. (b), requisite provisions of plan; and in subsec. (c), attainment of applicable standard not later than July 1, 1987.

1977—Subsec. (b)(4). Pub. L. 95–190, §14(a)(55), substituted "subsection (a)" for "paragraph (1)".

Subsec. (c). Pub. L. 95–190, §14(a)(56), substituted "December 31" for "July 1".


Statutory Notes and Related Subsidiaries

Nonattainment Areas

Pub. L. 95–95, title I, §129(a), Aug. 7, 1977, 91 Stat. 745, as amended by Pub. L. 95–190, §14(b)(2), (3), Nov. 16, 1977, 91 Stat. 1404, provided that:

"(1) Before July 1, 1979, the interpretative regulation of the Administrator of the Environmental Protection Agency published in 41 Federal Register 55524–30, December 21, 1976, as may be modified by rule of the Administrator, shall apply except that the baseline to be used for determination of appropriate emission offsets under such regulation shall be the applicable implementation plan of the State in effect at the time of application for a permit by a proposed major stationary source (within the meaning of section 302 of the Clean Air Act) [section 7602 of this title].

"(2) Before July 1, 1979, the requirements of the regulation referred to in paragraph (1) shall be waived by the Administrator with respect to any pollutant if he determines that the State has—

"(A) an inventory of emissions of the applicable pollutant for each nonattainment area (as defined in section 171 of the Clean Air Act [section 7501 of this title]) that identifies the type, quantity, and source of such pollutant so as to provide information sufficient to demonstrate that the requirements of subparagraph (C) are being met;

"(B) an enforceable permit program which—

"(i) requires new or modified major stationary sources to meet emission limitations at least as stringent as required under the permit requirements referred to in paragraphs (2) and (3) of section 173 of the Clean Air Act [section 7503 of this title] (relating to lowest achievable emission rate and compliance by other sources) and which assures compliance with the annual reduction requirements of subparagraph (C); and

"(ii) requires existing sources to achieve such reduction in emissions in the area as may be obtained through the adoption, at a minimum of reasonably available control technology, and

"(C) a program which requires reductions in total allowable emissions in the area prior to July 1, 1979, so as to provide for the same level of emission reduction as would result from the application of the regulation referred to in paragraph (1).

The Administrator shall terminate such waiver if in his judgment the reduction in emissions actually being attained is less than the reduction on which the waiver was conditioned pursuant to subparagraph (C), or if the Administrator determines that the State is no longer in compliance with any requirement of this paragraph. Upon application by the State, the Administrator may reinstate a waiver terminated under the preceding sentence if he is satisfied that such State is in compliance with all requirements of this subsection.

"(3) Operating permits may be issued to those applicants who were properly granted construction permits, in accordance with the law and applicable regulations in effect at the time granted, for construction of a new or modified source in areas exceeding national primary air quality standards on or before the date of the enactment of this Act [Aug. 7, 1977] if such construction permits were granted prior to the date of the enactment of this Act and the person issued any such permit is able to demonstrate that the emissions from the source will be within the limitations set forth in such construction permit."

State Implementation Plan Revision

Pub. L. 95–95, title I, §129(c), Aug. 7, 1977, 91 Stat. 750, as amended by Pub. L. 95–190, §14(b)(4), Nov. 16, 1977, 91 Stat. 1405, provided that: "Notwithstanding the requirements of section 406(d)(2) [set out as an Effective Date of 1977 Amendment note under section 7401 of this title] (relating to date required for submission of certain implementation plan revisions), for purposes of section 110(a)(2) of the Clean Air Act [section 7410(a)(2) of this title] each State in which there is any nonattainment area (as defined in part D of title I of the Clean Air Act) [this part] shall adopt and submit an implementation plan revision which meets the requirements of section 110(a)(2)(I) [section 7410(a)(2)(I) of this title] and part D of title I of the Clean Air Act [this part] not later than January 1, 1979. In the case of any State for which a plan revision adopted and submitted before such date has made the demonstration required under section 172(a)(2) of the Clean Air Act [subsec. (a)(2) of this section] (respecting impossibility of attainment before 1983), such State shall adopt and submit to the Administrator a plan revision before July 1, 1982, which meets the requirements of section 172(b) and (c) of such Act [subsecs. (b) and (c) of this section]."

§7503. Permit requirements

(a) In general

The permit program required by section 7502(b)(6) 1 of this title shall provide that permits to construct and operate may be issued if—

(1) in accordance with regulations issued by the Administrator for the determination of baseline emissions in a manner consistent with the assumptions underlying the applicable implementation plan approved under section 7410 of this title and this part, the permitting agency determines that—

(A) by the time the source is to commence operation, sufficient offsetting emissions reductions have been obtained, such that total allowable emissions from existing sources in the region, from new or modified sources which are not major emitting facilities, and from the proposed source will be sufficiently less than total emissions from existing sources (as determined in accordance with the regulations under this paragraph) prior to the application for such permit to construct or modify so as to represent (when considered together with the plan provisions required under section 7502 of this title) reasonable further progress (as defined in section 7501 of this title); or

(B) in the case of a new or modified major stationary source which is located in a zone (within the nonattainment area) identified by the Administrator, in consultation with the Secretary of Housing and Urban Development, as a zone to which economic development should be targeted, that emissions of such pollutant resulting from the proposed new or modified major stationary source will not cause or contribute to emissions levels which exceed the allowance permitted for such pollutant for such area from new or modified major stationary sources under section 7502(c) of this title;


(2) the proposed source is required to comply with the lowest achievable emission rate;

(3) the owner or operator of the proposed new or modified source has demonstrated that all major stationary sources owned or operated by such person (or by any entity controlling, controlled by, or under common control with such person) in such State are subject to emission limitations and are in compliance, or on a schedule for compliance, with all applicable emission limitations and standards under this chapter; and 2

(4) the Administrator has not determined that the applicable implementation plan is not being adequately implemented for the nonattainment area in which the proposed source is to be constructed or modified in accordance with the requirements of this part; and

(5) an analysis of alternative sites, sizes, production processes, and environmental control techniques for such proposed source demonstrates that benefits of the proposed source significantly outweigh the environmental and social costs imposed as a result of its location, construction, or modification.


Any emission reductions required as a precondition of the issuance of a permit under paragraph (1) shall be federally enforceable before such permit may be issued.

(b) Prohibition on use of old growth allowances

Any growth allowance included in an applicable implementation plan to meet the requirements of section 7502(b)(5) of this title (as in effect immediately before November 15, 1990) shall not be valid for use in any area that received or receives a notice under section 7410(a)(2)(H)(ii) of this title (as in effect immediately before November 15, 1990) or under section 7410(k)(1) of this title that its applicable implementation plan containing such allowance is substantially inadequate.

(c) Offsets

(1) The owner or operator of a new or modified major stationary source may comply with any offset requirement in effect under this part for increased emissions of any air pollutant only by obtaining emission reductions of such air pollutant from the same source or other sources in the same nonattainment area, except that the State may allow the owner or operator of a source to obtain such emission reductions in another nonattainment area if (A) the other area has an equal or higher nonattainment classification than the area in which the source is located and (B) emissions from such other area contribute to a violation of the national ambient air quality standard in the nonattainment area in which the source is located. Such emission reductions shall be, by the time a new or modified source commences operation, in effect and enforceable and shall assure that the total tonnage of increased emissions of the air pollutant from the new or modified source shall be offset by an equal or greater reduction, as applicable, in the actual emissions of such air pollutant from the same or other sources in the area.

(2) Emission reductions otherwise required by this chapter shall not be creditable as emissions reductions for purposes of any such offset requirement. Incidental emission reductions which are not otherwise required by this chapter shall be creditable as emission reductions for such purposes if such emission reductions meet the requirements of paragraph (1).

(d) Control technology information

The State shall provide that control technology information from permits issued under this section will be promptly submitted to the Administrator for purposes of making such information available through the RACT/BACT/LAER clearinghouse to other States and to the general public.

(e) Rocket engines or motors

The permitting authority of a State shall allow a source to offset by alternative or innovative means emission increases from rocket engine and motor firing, and cleaning related to such firing, at an existing or modified major source that tests rocket engines or motors under the following conditions:

(1) Any modification proposed is solely for the purpose of expanding the testing of rocket engines or motors at an existing source that is permitted to test such engines on November 15, 1990.

(2) The source demonstrates to the satisfaction of the permitting authority of the State that it has used all reasonable means to obtain and utilize offsets, as determined on an annual basis, for the emissions increases beyond allowable levels, that all available offsets are being used, and that sufficient offsets are not available to the source.

(3) The source has obtained a written finding from the Department of Defense, Department of Transportation, National Aeronautics and Space Administration or other appropriate Federal agency, that the testing of rocket motors or engines at the facility is required for a program essential to the national security.

(4) The source will comply with an alternative measure, imposed by the permitting authority, designed to offset any emission increases beyond permitted levels not directly offset by the source. In lieu of imposing any alternative offset measures, the permitting authority may impose an emissions fee to be paid to such authority of a State which shall be an amount no greater than 1.5 times the average cost of stationary source control measures adopted in that area during the previous 3 years. The permitting authority shall utilize the fees in a manner that maximizes the emissions reductions in that area.

(July 14, 1955, ch. 360, title I, §173, as added Pub. L. 95–95, title I, §129(b), Aug. 7, 1977, 91 Stat. 748; amended Pub. L. 95–190, §14(a)(57), (58), Nov. 16, 1977, 91 Stat. 1403; Pub. L. 101–549, title I, §102(c), Nov. 15, 1990, 104 Stat. 2415.)


Editorial Notes

References in Text

Section 7502(b) of this title, referred to in subsec. (a), was amended generally by Pub. L. 101–549, title I, §102(b), Nov. 15, 1990, 104 Stat. 2412, and, as so amended, does not contain a par. (6). See section 7502(c)(5) of this title.

Amendments

1990Pub. L. 101–549, §102(c)(1), made technical amendment to section catchline.

Pub. L. 101–549, §102(c)(2), (8), designated existing provisions as subsec. (a), inserted heading, and substituted "(1) shall be federally enforceable" for "(1)(A) shall be legally binding" in last sentence.

Subsec. (a)(1). Pub. L. 101–549, §102(c)(3), inserted at beginning "in accordance with regulations issued by the Administrator for the determination of baseline emissions in a manner consistent with the assumptions underlying the applicable implementation plan approved under section 7410 of this title and this part,".

Subsec. (a)(1)(A). Pub. L. 101–549, §102(c)(4), inserted "sufficient offsetting emissions reductions have been obtained, such that" after "to commence operation," and substituted "(as determined in accordance with the regulations under this paragraph)" for "allowed under the applicable implementation plan".

Subsec. (a)(1)(B). Pub. L. 101–549, §102(c)(5), inserted at beginning "in the case of a new or modified major stationary source which is located in a zone (within the nonattainment area) identified by the Administrator, in consultation with the Secretary of Housing and Urban Development, as a zone to which economic development should be targeted," and substituted "7502(c)" for "7502(b)".

Subsec. (a)(4). Pub. L. 101–549, §102(c)(6), inserted at beginning "the Administrator has not determined that", substituted "not being adequately implemented" for "being carried out", and substituted "; and" for period at end.

Subsec. (a)(5). Pub. L. 101–549, §102(c)(7), added par. (5).

Subsec. (b). Pub. L. 101–549, §102(c)(9), added subsec. (b).

Subsecs. (c) to (e). Pub. L. 101–549, §102(c)(10), added subsecs. (c) to (e).

1977—Par. (1)(A). Pub. L. 95–190, §14(a)(57), inserted "or modified" after "from new" and "applicable" before "implementation plan", and substituted "source" for "facility" wherever appearing.

Par. (4). Pub. L. 95–190, §14(a)(58), added par. (4).


Statutory Notes and Related Subsidiaries

Failure To Attain National Primary Ambient Air Quality Standards Under Clean Air Act

Pub. L. 100–202, §101(f) [title II], Dec. 22, 1987, 101 Stat. 1329–187, 1329-199, provided that: "No restriction or prohibition on construction, permitting, or funding under sections 110(a)(2)(I), 173(4), 176(a), 176(b), or 316 of the Clean Air Act [sections 7410(a)(2)(I), 7503(4), 7506(a), (b), 7616 of this title] shall be imposed or take effect during the period prior to August 31, 1988, by reason of (1) the failure of any nonattainment area to attain the national primary ambient air quality standard under the Clean Air Act [this chapter] for photochemical oxidants (ozone) or carbon monoxide (or both) by December 31, 1987, (2) the failure of any State to adopt and submit to the Administrator of the Environmental Protection Agency an implementation plan that meets the requirements of part D of title I of such Act [this part] and provides for attainment of such standards by December 31, 1987, (3) the failure of any State or designated local government to implement the applicable implementation plan, or (4) any combination of the foregoing. During such period and consistent with the preceding sentence, the issuance of a permit (including required offsets) under section 173 of such Act [this section] for the construction or modification of a source in a nonattainment area shall not be denied solely or partially by reason of the reference contained in section 171(l) of such Act [section 7501(1) of this title] to the applicable date established in section 172(a) [section 7502(a) of this title]. This subsection [probably means the first 3 sentences of this note] shall not apply to any restriction or prohibition in effect under sections 110(a)(2)(I), 173(4), 176(a), 176(b), or 316 of such Act prior to the enactment of this section [Dec. 22, 1987]. Prior to August 31, 1988, the Administrator of the Environmental Protection Agency shall evaluate air quality data and make determinations with respect to which areas throughout the nation have attained, or failed to attain, either or both of the national primary ambient air quality standards referred to in subsection (a) [probably means the first 3 sentences of this note] and shall take appropriate steps to designate those areas failing to attain either or both of such standards as nonattainment areas within the meaning of part D of title I of the Clean Air Act."

1 See References in Text note below.

2 So in original. The word "and" probably should not appear.

§7504. Planning procedures

(a) In general

For any ozone, carbon monoxide, or PM–10 nonattainment area, the State containing such area and elected officials of affected local governments shall, before the date required for submittal of the inventory described under sections 7511a(a)(1) and 7512a(a)(1) of this title, jointly review and update as necessary the planning procedures adopted pursuant to this subsection as in effect immediately before November 15, 1990, or develop new planning procedures pursuant to this subsection, as appropriate. In preparing such procedures the State and local elected officials shall determine which elements of a revised implementation plan will be developed, adopted, and implemented (through means including enforcement) by the State and which by local governments or regional agencies, or any combination of local governments, regional agencies, or the State. The implementation plan required by this part shall be prepared by an organization certified by the State, in consultation with elected officials of local governments and in accordance with the determination under the second sentence of this subsection. Such organization shall include elected officials of local governments in the affected area, and representatives of the State air quality planning agency, the State transportation planning agency, the metropolitan planning organization designated to conduct the continuing, cooperative and comprehensive transportation planning process for the area under section 134 of title 23, the organization responsible for the air quality maintenance planning process under regulations implementing this chapter, and any other organization with responsibilities for developing, submitting, or implementing the plan required by this part. Such organization may be one that carried out these functions before November 15, 1990.

(b) Coordination

The preparation of implementation plan provisions and subsequent plan revisions under the continuing transportation-air quality planning process described in section 7408(e) of this title shall be coordinated with the continuing, cooperative and comprehensive transportation planning process required under section 134 of title 23, and such planning processes shall take into account the requirements of this part.

(c) Joint planning

In the case of a nonattainment area that is included within more than one State, the affected States may jointly, through interstate compact or otherwise, undertake and implement all or part of the planning procedures described in this section.

(July 14, 1955, ch. 360, title I, §174, as added Pub. L. 95–95, title I, §129(b), Aug. 7, 1977, 91 Stat. 748; amended Pub. L. 101–549, title I, §102(d), Nov. 15, 1990, 104 Stat. 2417.)


Editorial Notes

Amendments

1990Pub. L. 101–549 amended section generally, substituting present provisions for provisions which related to: in subsec. (a), preparation of implementation plan by designated organization; and in subsec. (b), coordination of plan preparation.

§7505. Environmental Protection Agency grants

(a) Plan revision development costs

The Administrator shall make grants to any organization of local elected officials with transportation or air quality maintenance planning responsibilities recognized by the State under section 7504(a) of this title for payment of the reasonable costs of developing a plan revision under this part.

(b) Uses of grant funds

The amount granted to any organization under subsection (a) shall be 100 percent of any additional costs of developing a plan revision under this part for the first two fiscal years following receipt of the grant under this paragraph, and shall supplement any funds available under Federal law to such organization for transportation or air quality maintenance planning. Grants under this section shall not be used for construction.

(July 14, 1955, ch. 360, title I, §175, as added Pub. L. 95–95, title I, §129(b), Aug. 7, 1977, 91 Stat. 749.)

§7505a. Maintenance plans

(a) Plan revision

Each State which submits a request under section 7407(d) of this title for redesignation of a nonattainment area for any air pollutant as an area which has attained the national primary ambient air quality standard for that air pollutant shall also submit a revision of the applicable State implementation plan to provide for the maintenance of the national primary ambient air quality standard for such air pollutant in the area concerned for at least 10 years after the redesignation. The plan shall contain such additional measures, if any, as may be necessary to ensure such maintenance.

(b) Subsequent plan revisions

8 years after redesignation of any area as an attainment area under section 7407(d) of this title, the State shall submit to the Administrator an additional revision of the applicable State implementation plan for maintaining the national primary ambient air quality standard for 10 years after the expiration of the 10-year period referred to in subsection (a).

(c) Nonattainment requirements applicable pending plan approval

Until such plan revision is approved and an area is redesignated as attainment for any area designated as a nonattainment area, the requirements of this part shall continue in force and effect with respect to such area.

(d) Contingency provisions

Each plan revision submitted under this section shall contain such contingency provisions as the Administrator deems necessary to assure that the State will promptly correct any violation of the standard which occurs after the redesignation of the area as an attainment area. Such provisions shall include a requirement that the State will implement all measures with respect to the control of the air pollutant concerned which were contained in the State implementation plan for the area before redesignation of the area as an attainment area. The failure of any area redesignated as an attainment area to maintain the national ambient air quality standard concerned shall not result in a requirement that the State revise its State implementation plan unless the Administrator, in the Administrator's discretion, requires the State to submit a revised State implementation plan.

(July 14, 1955, ch. 360, title I, §175A, as added Pub. L. 101–549, title I, §102(e), Nov. 15, 1990, 104 Stat. 2418.)

§7506. Limitations on certain Federal assistance

(a), (b) Repealed. Pub. L. 101–549, title I, §110(4), Nov. 15, 1990, 104 Stat. 2470

(c) Activities not conforming to approved or promulgated plans

(1) No department, agency, or instrumentality of the Federal Government shall engage in, support in any way or provide financial assistance for, license or permit, or approve, any activity which does not conform to an implementation plan after it has been approved or promulgated under section 7410 of this title. No metropolitan planning organization designated under section 134 of title 23, shall give its approval to any project, program, or plan which does not conform to an implementation plan approved or promulgated under section 7410 of this title. The assurance of conformity to such an implementation plan shall be an affirmative responsibility of the head of such department, agency, or instrumentality. Conformity to an implementation plan means—

(A) conformity to an implementation plan's purpose of eliminating or reducing the severity and number of violations of the national ambient air quality standards and achieving expeditious attainment of such standards; and

(B) that such activities will not—

(i) cause or contribute to any new violation of any standard in any area;

(ii) increase the frequency or severity of any existing violation of any standard in any area; or

(iii) delay timely attainment of any standard or any required interim emission reductions or other milestones in any area.


The determination of conformity shall be based on the most recent estimates of emissions, and such estimates shall be determined from the most recent population, employment, travel and congestion estimates as determined by the metropolitan planning organization or other agency authorized to make such estimates.

(2) Any transportation plan or program developed pursuant to title 23 or chapter 53 of title 49 shall implement the transportation provisions of any applicable implementation plan approved under this chapter applicable to all or part of the area covered by such transportation plan or program. No Federal agency may approve, accept or fund any transportation plan, program or project unless such plan, program or project has been found to conform to any applicable implementation plan in effect under this chapter. In particular—

(A) no transportation plan or transportation improvement program may be adopted by a metropolitan planning organization designated under title 23 or chapter 53 of title 49, or be found to be in conformity by a metropolitan planning organization until a final determination has been made that emissions expected from implementation of such plans and programs are consistent with estimates of emissions from motor vehicles and necessary emissions reductions contained in the applicable implementation plan, and that the plan or program will conform to the requirements of paragraph (1)(B);

(B) no metropolitan planning organization or other recipient of funds under title 23 or chapter 53 of title 49 shall adopt or approve a transportation improvement program of projects until it determines that such program provides for timely implementation of transportation control measures consistent with schedules included in the applicable implementation plan;

(C) a transportation project may be adopted or approved by a metropolitan planning organization or any recipient of funds designated under title 23 or chapter 53 of title 49, or found in conformity by a metropolitan planning organization or approved, accepted, or funded by the Department of Transportation only if it meets either the requirements of subparagraph (D) or the following requirements—

(i) such a project comes from a conforming plan and program;

(ii) the design concept and scope of such project have not changed significantly since the conformity finding regarding the plan and program from which the project derived; and

(iii) the design concept and scope of such project at the time of the conformity determination for the program was adequate to determine emissions.


(D) Any project not referred to in subparagraph (C) shall be treated as conforming to the applicable implementation plan only if it is demonstrated that the projected emissions from such project, when considered together with emissions projected for the conforming transportation plans and programs within the nonattainment area, do not cause such plans and programs to exceed the emission reduction projections and schedules assigned to such plans and programs in the applicable implementation plan.

(E) The appropriate metropolitan planning organization shall redetermine conformity of existing transportation plans and programs not later than 2 years after the date on which the Administrator—

(i) finds a motor vehicle emissions budget to be adequate in accordance with section 93.118(e)(4) of title 40, Code of Federal Regulations (as in effect on October 1, 2004);

(ii) approves an implementation plan that establishes a motor vehicle emissions budget if that budget has not yet been determined to be adequate in accordance with clause (i); or

(iii) promulgates an implementation plan that establishes or revises a motor vehicle emissions budget.


(3) Until such time as the implementation plan revision referred to in paragraph (4)(C) 1 is approved, conformity of such plans, programs, and projects will be demonstrated if—

(A) the transportation plans and programs—

(i) are consistent with the most recent estimates of mobile source emissions;

(ii) provide for the expeditious implementation of transportation control measures in the applicable implementation plan; and

(iii) with respect to ozone and carbon monoxide nonattainment areas, contribute to annual emissions reductions consistent with sections 7511a(b)(1) and 7512a(a)(7) of this title; and


(B) the transportation projects—

(i) come from a conforming transportation plan and program as defined in subparagraph (A) or for 12 months after November 15, 1990, from a transportation program found to conform within 3 years prior to November 15, 1990; and

(ii) in carbon monoxide nonattainment areas, eliminate or reduce the severity and number of violations of the carbon monoxide standards in the area substantially affected by the project.


With regard to subparagraph (B)(ii), such determination may be made as part of either the conformity determination for the transportation program or for the individual project taken as a whole during the environmental review phase of project development.


(4) Criteria and procedures for determining conformity.—

(A) In general.—The Administrator shall promulgate, and periodically update, criteria and procedures for determining conformity (except in the case of transportation plans, programs, and projects) of, and for keeping the Administrator informed about, the activities referred to in paragraph (1).

(B) Transportation plans, programs, and projects.—The Administrator, with the concurrence of the Secretary of Transportation, shall promulgate, and periodically update, criteria and procedures for demonstrating and assuring conformity in the case of transportation plans, programs, and projects.

(C) Civil action to compel promulgation.—A civil action may be brought against the Administrator and the Secretary of Transportation under section 7604 of this title to compel promulgation of such criteria and procedures and the Federal district court shall have jurisdiction to order such promulgation.

(D) The procedures and criteria shall, at a minimum—

(i) address the consultation procedures to be undertaken by metropolitan planning organizations and the Secretary of Transportation with State and local air quality agencies and State departments of transportation before such organizations and the Secretary make conformity determinations;

(ii) address the appropriate frequency for making conformity determinations, but the frequency for making conformity determinations on updated transportation plans and programs shall be every 4 years, except in a case in which—

(I) the metropolitan planning organization elects to update a transportation plan or program more frequently; or

(II) the metropolitan planning organization is required to determine conformity in accordance with paragraph (2)(E); and


(iii) address how conformity determinations will be made with respect to maintenance plans.


(E) Inclusion of criteria and procedures in sip.—Not later than 2 years after August 10, 2005, the procedures under subparagraph (A) shall include a requirement that each State include in the State implementation plan criteria and procedures for consultation required by subparagraph (D)(i), and enforcement and enforceability (pursuant to sections 93.125(c) and 93.122(a)(4)(ii) of title 40, Code of Federal Regulations) in accordance with the Administrator's criteria and procedures for consultation, enforcement and enforceability.

(F) Compliance with the rules of the Administrator for determining the conformity of transportation plans, programs, and projects funded or approved under title 23 or chapter 53 of title 49 to State or Federal implementation plans shall not be required for traffic signal synchronization projects prior to the funding, approval or implementation of such projects. The supporting regional emissions analysis for any conformity determination made with respect to a transportation plan, program, or project shall consider the effect on emissions of any such project funded, approved, or implemented prior to the conformity determination.


(5) Applicability.—This subsection shall apply only with respect to—

(A) a nonattainment area and each pollutant for which the area is designated as a nonattainment area; and

(B) an area that was designated as a nonattainment area but that was later redesignated by the Administrator as an attainment area and that is required to develop a maintenance plan under section 7505a of this title with respect to the specific pollutant for which the area was designated nonattainment.


(6) Notwithstanding paragraph 5,2 this subsection shall not apply with respect to an area designated nonattainment under section 7407(d)(1) of this title until 1 year after that area is first designated nonattainment for a specific national ambient air quality standard. This paragraph only applies with respect to the national ambient air quality standard for which an area is newly designated nonattainment and does not affect the area's requirements with respect to all other national ambient air quality standards for which the area is designated nonattainment or has been redesignated from nonattainment to attainment with a maintenance plan pursuant to section 7505a 1 of this title (including any pre-existing national ambient air quality standard for a pollutant for which a new or revised standard has been issued).

(7) Conformity horizon for transportation plans.—

(A) In general.—Each conformity determination required under this section for a transportation plan under section 134(i) of title 23 or section 5303(i) of title 49 shall require a demonstration of conformity for the period ending on either the final year of the transportation plan, or at the election of the metropolitan planning organization, after consultation with the air pollution control agency and solicitation of public comments and consideration of such comments, the longest of the following periods:

(i) The first 10-year period of any such transportation plan.

(ii) The latest year in the implementation plan applicable to the area that contains a motor vehicle emission budget.

(iii) The year after the completion date of a regionally significant project if the project is included in the transportation improvement program or the project requires approval before the subsequent conformity determination.


(B) Regional emissions analysis.—The conformity determination shall be accompanied by a regional emissions analysis for the last year of the transportation plan and for any year shown to exceed emission budgets by a prior analysis, if such year extends beyond the applicable period as determined under subparagraph (A).

(C) Exception.—In any case in which an area has a revision to an implementation plan under section 7505a(b) of this title and the Administrator has found the motor vehicles emissions budgets from that revision to be adequate in accordance with section 93.118(e)(4) of title 40, Code of Federal Regulations (as in effect on October 1, 2004), or has approved the revision, the demonstration of conformity at the election of the metropolitan planning organization, after consultation with the air pollution control agency and solicitation of public comments and consideration of such comments, shall be required to extend only through the last year of the implementation plan required under section 7505a(b) of this title.

(D) Effect of election.—Any election by a metropolitan planning organization under this paragraph shall continue in effect until the metropolitan planning organization elects otherwise.

(E) Air pollution control agency defined.—In this paragraph, the term "air pollution control agency" means an air pollution control agency (as defined in section 7602(b) of this title) that is responsible for developing plans or controlling air pollution within the area covered by a transportation plan.


(8) Substitution of transportation control measures.—

(A) In general.—Transportation control measures that are specified in an implementation plan may be replaced or added to the implementation plan with alternate or additional transportation control measures—

(i) if the substitute measures achieve equivalent or greater emissions reductions than the control measure to be replaced, as demonstrated with an emissions impact analysis that is consistent with the current methodology used for evaluating the replaced control measure in the implementation plan;

(ii) if the substitute control measures are implemented—

(I) in accordance with a schedule that is consistent with the schedule provided for control measures in the implementation plan; or

(II) if the implementation plan date for implementation of the control measure to be replaced has passed, as soon as practicable after the implementation plan date but not later than the date on which emission reductions are necessary to achieve the purpose of the implementation plan;


(iii) if the substitute and additional control measures are accompanied with evidence of adequate personnel and funding and authority under State or local law to implement, monitor, and enforce the control measures;

(iv) if the substitute and additional control measures were developed through a collaborative process that included—

(I) participation by representatives of all affected jurisdictions (including local air pollution control agencies, the State air pollution control agency, and State and local transportation agencies);

(II) consultation with the Administrator; and

(III) reasonable public notice and opportunity for comment; and


(v) if the metropolitan planning organization, State air pollution control agency, and the Administrator concur with the equivalency of the substitute or additional control measures.


(B) Adoption.—(i) Concurrence by the metropolitan planning organization, State air pollution control agency and the Administrator as required by subparagraph (A)(v) shall constitute adoption of the substitute or additional control measures so long as the requirements of subparagraphs (A)(i), (A)(ii), (A)(iii) and (A)(iv) are met.

(ii) Once adopted, the substitute or additional control measures become, by operation of law, part of the State implementation plan and become federally enforceable.

(iii) Within 90 days of its concurrence under subparagraph (A)(v), the State air pollution control agency shall submit the substitute or additional control measure to the Administrator for incorporation in the codification of the applicable implementation plan. Nothwithstanding 3 any other provision of this chapter, no additional State process shall be necessary to support such revision to the applicable plan.

(C) No requirement for express permission.—The substitution or addition of a transportation control measure in accordance with this paragraph and the funding or approval of such a control measure shall not be contingent on the existence of any provision in the applicable implementation plan that expressly permits such a substitution or addition.

(D) No requirement for new conformity determination.—The substitution or addition of a transportation control measure in accordance with this paragraph shall not require—

(i) a new conformity determination for the transportation plan; or

(ii) a revision of the implementation plan.


(E) Continuation of control measure being replaced.—A control measure that is being replaced by a substitute control measure under this paragraph shall remain in effect until the substitute control measure is adopted by the State pursuant to subparagraph (B).

(F) Effect of adoption.—Adoption of a substitute control measure shall constitute rescission of the previously applicable control measure.


(9) Lapse of conformity.—If a conformity determination required under this subsection for a transportation plan under section 134(i) of title 23 or section 5303(i) of title 49 or a transportation improvement program under section 134(j) of such title 23 or under section 5303(j) of such title 49 is not made by the applicable deadline and such failure is not corrected by additional measures to either reduce motor vehicle emissions sufficient to demonstrate compliance with the requirements of this subsection within 12 months after such deadline or other measures sufficient to correct such failures, the transportation plan shall lapse.

(10) Lapse.—In this subsection, the term "lapse" means that the conformity determination for a transportation plan or transportation improvement program has expired, and thus there is no currently conforming transportation plan or transportation improvement program.

(d) Priority of achieving and maintaining national primary ambient air quality standards

Each department, agency, or instrumentality of the Federal Government having authority to conduct or support any program with air-quality related transportation consequences shall give priority in the exercise of such authority, consistent with statutory requirements for allocation among States or other jurisdictions, to the implementation of those portions of plans prepared under this section to achieve and maintain the national primary ambient air-quality standard. This paragraph extends to, but is not limited to, authority exercised under chapter 53 of title 49, title 23, and the Housing and Urban Development Act.

(July 14, 1955, ch. 360, title I, §176, as added Pub. L. 95–95, title I, §129(b), Aug. 7, 1977, 91 Stat. 749; amended Pub. L. 95–190, §14(a)(59), Nov. 16, 1977, 91 Stat. 1403; Pub. L. 101–549, title I, §§101(f), 110(4), Nov. 15, 1990, 104 Stat. 2409, 2470; Pub. L. 104–59, title III, §305(b), Nov. 28, 1995, 109 Stat. 580; Pub. L. 104–260, §1, Oct. 9, 1996, 110 Stat. 3175; Pub. L. 106–377, §1(a)(1) [title III], Oct. 27, 2000, 114 Stat. 1441, 1441A-44; Pub. L. 109–59, title VI, §6011(a)–(f), Aug. 10, 2005, 119 Stat. 1878–1881.)


Editorial Notes

References in Text

Paragraph (4) of subsec. (c), referred to in subsec. (c)(3), was amended by Pub. L. 109–59, title VI, §6011(f), Aug. 10, 2005, 119 Stat. 1881, to redesignate subpar. (C) as (E), strike it out, and add new subpars. (C) and (E). See 2005 Amendment notes below.

Section 7505a of this title, referred to in subsec. (c)(6), was in the original "section 175(A)" and was translated as reading "section 175A", meaning section 175A of act July 14, 1955, which is classified to section 7505a of this title, to reflect the probable intent of Congress.

The Housing and Urban Development Act, referred to in subsec. (d), may be the name for a series of acts sharing the same name but enacted in different years by Pub. L. 89–117, Aug. 10, 1965, 79 Stat. 451; Pub. L. 90–448, Aug. 1, 1968, 82 Stat. 476; Pub. L. 91–152, Dec. 24, 1969, 83 Stat. 379; and Pub. L. 91–609, Dec. 31, 1970, 84 Stat. 1770, respectively. For complete classification of these Acts to the Code, see Short Title notes set out under section 1701 of Title 12, Banks and Banking, and Tables.

Codification

In subsecs. (c)(2) and (d), "chapter 53 of title 49" substituted for "the Urban Mass Transportation Act [49 App. U.S.C. 1601 et seq.]" and in subsec. (c)(4)(F) substituted for "Federal Transit Act" on authority of Pub. L. 103–272, §6(b), July 5, 1994, 108 Stat. 1378 (the first section of which enacted subtitles II, III, and V to X of Title 49, Transportation), and of Pub. L. 102–240, title III, §3003(b), Dec. 18, 1991, 105 Stat. 2088, which provided that references in laws to the Urban Mass Transportation Act of 1964 be deemed to be references to the Federal Transit Act.

Amendments

2005—Subsec. (c)(2)(E). Pub. L. 109–59, §6011(a), added subpar. (E).

Subsec. (c)(4). Pub. L. 109–59, §6011(f)(1)–(3), inserted par. (4) and subpar. (A) headings, in first sentence substituted "The Administrator shall promulgate, and periodically update," for "No later than one year after November 15, 1990, the Administrator shall promulgate", designated second sentence as subpar. (B), inserted heading, substituted "The Administrator, with the concurrence of the Secretary of Transportation, shall promulgate, and periodically update," for "No later than one year after November 15, 1990, the Administrator, with the concurrence of the Secretary of Transportation, shall promulgate", designated third sentence as subpar. (C), inserted heading, substituted "A civil action" for "A suit", and redesignated former subpars. (B) to (D) as (D) to (F), respectively.

Subsec. (c)(4)(B)(ii). Pub. L. 109–59, §6011(b), amended cl. (ii) generally. Prior to amendment, cl. (ii) read as follows: "address the appropriate frequency for making conformity determinations, but in no case shall such determinations for transportation plans and programs be less frequent than every three years; and".

Subsec. (c)(4)(E). Pub. L. 109–59, §6011(f)(4), added subpar. (E) and struck out former subpar. (E) which read as follows: "Such procedures shall also include a requirement that each State shall submit to the Administrator and the Secretary of Transportation within 24 months of November 15, 1990, a revision to its implementation plan that includes criteria and procedures for assessing the conformity of any plan, program, or project subject to the conformity requirements of this subsection."

Subsec. (c)(7) to (10). Pub. L. 109–59, §6011(c)–(e), added pars. (7) to (10).

2000—Subsec. (c)(6). Pub. L. 106–377 added par. (6).

1996—Subsec. (c)(4)(D). Pub. L. 104–260 added subpar. (D).

1995—Subsec. (c)(5). Pub. L. 104–59 added par. (5).

1990—Subsecs. (a), (b). Pub. L. 101–549, §110(4), struck out subsec. (a) which related to approval of projects or award of grants, and subsec. (b) which related to implementation of approved or promulgated plans.

Subsec. (c). Pub. L. 101–549, §101(f), designated existing provisions as par. (1), struck out "(1)", "(2)", "(3)", and "(4)" before "engage in", "support in", "license or", and "approve, any", respectively, substituted "conform to an implementation plan after it" for "conform to a plan after it", "conform to an implementation plan approved" for "conform to a plan approved", and "conformity to such an implementation plan shall" for "conformity to such a plan shall", inserted "Conformity to an implementation plan means—" followed immediately by subpars. (A) and (B) and closing provisions relating to determination of conformity being based on recent estimates of emissions and the determination of such estimates, and added pars. (2) to (4).

1977—Subsec. (a)(1). Pub. L. 95–190 inserted "national" before "primary".


Statutory Notes and Related Subsidiaries

Regulations

Pub. L. 109–59, title VI, §6011(g), Aug. 10, 2005, 119 Stat. 1882, provided that: "Not later than 2 years after the date of enactment of this Act [Aug. 10, 2005], the Administrator of the Environmental Protection Agency shall promulgate revised regulations to implement the changes made by this section [amending this section]."

1 See References in Text note below.

2 So in original. Probably should be "paragraph (5),".

3 So in original. Probably should be "Notwithstanding".

§7506a. Interstate transport commissions

(a) Authority to establish interstate transport regions

Whenever, on the Administrator's own motion or by petition from the Governor of any State, the Administrator has reason to believe that the interstate transport of air pollutants from one or more States contributes significantly to a violation of a national ambient air quality standard in one or more other States, the Administrator may establish, by rule, a transport region for such pollutant that includes such States. The Administrator, on the Administrator's own motion or upon petition from the Governor of any State, or upon the recommendation of a transport commission established under subsection (b), may—

(1) add any State or portion of a State to any region established under this subsection whenever the Administrator has reason to believe that the interstate transport of air pollutants from such State significantly contributes to a violation of the standard in the transport region, or

(2) remove any State or portion of a State from the region whenever the Administrator has reason to believe that the control of emissions in that State or portion of the State pursuant to this section will not significantly contribute to the attainment of the standard in any area in the region.


The Administrator shall approve or disapprove any such petition or recommendation within 18 months of its receipt. The Administrator shall establish appropriate proceedings for public participation regarding such petitions and motions, including notice and comment.

(b) Transport commissions

(1) Establishment

Whenever the Administrator establishes a transport region under subsection (a), the Administrator shall establish a transport commission comprised of (at a minimum) each of the following members:

(A) The Governor of each State in the region or the designee of each such Governor.

(B) The Administrator or the Administrator's designee.

(C) The Regional Administrator (or the Administrator's designee) for each Regional Office for each Environmental Protection Agency Region affected by the transport region concerned.

(D) An air pollution control official representing each State in the region, appointed by the Governor.


Decisions of, and recommendations and requests to, the Administrator by each transport commission may be made only by a majority vote of all members other than the Administrator and the Regional Administrators (or designees thereof).

(2) Recommendations

The transport commission shall assess the degree of interstate transport of the pollutant or precursors to the pollutant throughout the transport region, assess strategies for mitigating the interstate pollution, and recommend to the Administrator such measures as the Commission determines to be necessary to ensure that the plans for the relevant States meet the requirements of section 7410(a)(2)(D) of this title. Such commission shall not be subject to the provisions of chapter 10 of title 5.

(c) Commission requests

A transport commission established under subsection (b) may request the Administrator to issue a finding under section 7410(k)(5) of this title that the implementation plan for one or more of the States in the transport region is substantially inadequate to meet the requirements of section 7410(a)(2)(D) of this title. The Administrator shall approve, disapprove, or partially approve and partially disapprove such a request within 18 months of its receipt and, to the extent the Administrator approves such request, issue the finding under section 7410(k)(5) of this title at the time of such approval. In acting on such request, the Administrator shall provide an opportunity for public participation and shall address each specific recommendation made by the commission. Approval or disapproval of such a request shall constitute final agency action within the meaning of section 7607(b) of this title.

(July 14, 1955, ch. 360, title I, §176A, as added Pub. L. 101–549, title I, §102(f)(1), Nov. 15, 1990, 104 Stat. 2419; amended Pub. L. 117–286, §4(a)(270), Dec. 27, 2022, 136 Stat. 4335.)


Editorial Notes

Amendments

2022—Subsec. (b)(2). Pub. L. 117–286 substituted "chapter 10 of title 5." for "the Federal Advisory Committee Act (5 U.S.C. App.)."

§7507. New motor vehicle emission standards in nonattainment areas

Notwithstanding section 7543(a) of this title, any State which has plan provisions approved under this part may adopt and enforce for any model year standards relating to control of emissions from new motor vehicles or new motor vehicle engines and take such other actions as are referred to in section 7543(a) of this title respecting such vehicles if—

(1) such standards are identical to the California standards for which a waiver has been granted for such model year, and

(2) California and such State adopt such standards at least two years before commencement of such model year (as determined by regulations of the Administrator).


Nothing in this section or in subchapter II of this chapter shall be construed as authorizing any such State to prohibit or limit, directly or indirectly, the manufacture or sale of a new motor vehicle or motor vehicle engine that is certified in California as meeting California standards, or to take any action of any kind to create, or have the effect of creating, a motor vehicle or motor vehicle engine different than a motor vehicle or engine certified in California under California standards (a "third vehicle") or otherwise create such a "third vehicle".

(July 14, 1955, ch. 360, title I, §177, as added Pub. L. 95–95, title I, §129(b), Aug. 7, 1977, 91 Stat. 750; amended Pub. L. 101–549, title II, §232, Nov. 15, 1990, 104 Stat. 2529.)


Editorial Notes

Amendments

1990Pub. L. 101–549 added sentence at end prohibiting States from limiting or prohibiting sale or manufacture of new vehicles or engines certified in California as having met California standards and from taking any actions where effect of those actions would be to create a "third vehicle".

§7508. Guidance documents

The Administrator shall issue guidance documents under section 7408 of this title for purposes of assisting States in implementing requirements of this part respecting the lowest achievable emission rate. Such a document shall be published not later than nine months after August 7, 1977, and shall be revised at least every two years thereafter.

(July 14, 1955, ch. 360, title I, §178, as added Pub. L. 95–95, title I, §129(b), Aug. 7, 1977, 91 Stat. 750.)

§7509. Sanctions and consequences of failure to attain

(a) State failure

For any implementation plan or plan revision required under this part (or required in response to a finding of substantial inadequacy as described in section 7410(k)(5) of this title), if the Administrator—

(1) finds that a State has failed, for an area designated nonattainment under section 7407(d) of this title, to submit a plan, or to submit 1 or more of the elements (as determined by the Administrator) required by the provisions of this chapter applicable to such an area, or has failed to make a submission for such an area that satisfies the minimum criteria established in relation to any such element under section 7410(k) of this title,

(2) disapproves a submission under section 7410(k) of this title, for an area designated nonattainment under section 7407 of this title, based on the submission's failure to meet one or more of the elements required by the provisions of this chapter applicable to such an area,

(3)(A) determines that a State has failed to make any submission as may be required under this chapter, other than one described under paragraph (1) or (2), including an adequate maintenance plan, or has failed to make any submission, as may be required under this chapter, other than one described under paragraph (1) or (2), that satisfies the minimum criteria established in relation to such submission under section 7410(k)(1)(A) of this title, or

(B) disapproves in whole or in part a submission described under subparagraph (A), or

(4) finds that any requirement of an approved plan (or approved part of a plan) is not being implemented,


unless such deficiency has been corrected within 18 months after the finding, disapproval, or determination referred to in paragraphs (1), (2), (3), and (4), one of the sanctions referred to in subsection (b) shall apply, as selected by the Administrator, until the Administrator determines that the State has come into compliance, except that if the Administrator finds a lack of good faith, sanctions under both paragraph (1) and paragraph (2) of subsection (b) shall apply until the Administrator determines that the State has come into compliance. If the Administrator has selected one of such sanctions and the deficiency has not been corrected within 6 months thereafter, sanctions under both paragraph (1) and paragraph (2) of subsection (b) shall apply until the Administrator determines that the State has come into compliance. In addition to any other sanction applicable as provided in this section, the Administrator may withhold all or part of the grants for support of air pollution planning and control programs that the Administrator may award under section 7405 of this title.

(b) Sanctions

The sanctions available to the Administrator as provided in subsection (a) are as follows:

(1) Highway sanctions

(A) The Administrator may impose a prohibition, applicable to a nonattainment area, on the approval by the Secretary of Transportation of any projects or the awarding by the Secretary of any grants, under title 23 other than projects or grants for safety where the Secretary determines, based on accident or other appropriate data submitted by the State, that the principal purpose of the project is an improvement in safety to resolve a demonstrated safety problem and likely will result in a significant reduction in, or avoidance of, accidents. Such prohibition shall become effective upon the selection by the Administrator of this sanction.

(B) In addition to safety, projects or grants that may be approved by the Secretary, notwithstanding the prohibition in subparagraph (A), are the following—

(i) capital programs for public transit;

(ii) construction or restriction of certain roads or lanes solely for the use of passenger buses or high occupancy vehicles;

(iii) planning for requirements for employers to reduce employee work-trip-related vehicle emissions;

(iv) highway ramp metering, traffic signalization, and related programs that improve traffic flow and achieve a net emission reduction;

(v) fringe and transportation corridor parking facilities serving multiple occupancy vehicle programs or transit operations;

(vi) programs to limit or restrict vehicle use in downtown areas or other areas of emission concentration particularly during periods of peak use, through road use charges, tolls, parking surcharges, or other pricing mechanisms, vehicle restricted zones or periods, or vehicle registration programs;

(vii) programs for breakdown and accident scene management, nonrecurring congestion, and vehicle information systems, to reduce congestion and emissions; and

(viii) such other transportation-related programs as the Administrator, in consultation with the Secretary of Transportation, finds would improve air quality and would not encourage single occupancy vehicle capacity.


In considering such measures, the State should seek to ensure adequate access to downtown, other commercial, and residential areas, and avoid increasing or relocating emissions and congestion rather than reducing them.

(2) Offsets

In applying the emissions offset requirements of section 7503 of this title to new or modified sources or emissions units for which a permit is required under this part, the ratio of emission reductions to increased emissions shall be at least 2 to 1.

(c) Notice of failure to attain

(1) As expeditiously as practicable after the applicable attainment date for any nonattainment area, but not later than 6 months after such date, the Administrator shall determine, based on the area's air quality as of the attainment date, whether the area attained the standard by that date.

(2) Upon making the determination under paragraph (1), the Administrator shall publish a notice in the Federal Register containing such determination and identifying each area that the Administrator has determined to have failed to attain. The Administrator may revise or supplement such determination at any time based on more complete information or analysis concerning the area's air quality as of the attainment date.

(d) Consequences for failure to attain

(1) Within 1 year after the Administrator publishes the notice under subsection (c)(2) (relating to notice of failure to attain), each State containing a nonattainment area shall submit a revision to the applicable implementation plan meeting the requirements of paragraph (2) of this subsection.

(2) The revision required under paragraph (1) shall meet the requirements of section 7410 of this title and section 7502 of this title. In addition, the revision shall include such additional measures as the Administrator may reasonably prescribe, including all measures that can be feasibly implemented in the area in light of technological achievability, costs, and any nonair quality and other air quality-related health and environmental impacts.

(3) The attainment date applicable to the revision required under paragraph (1) shall be the same as provided in the provisions of section 7502(a)(2) of this title, except that in applying such provisions the phrase "from the date of the notice under section 7509(c)(2) of this title" shall be substituted for the phrase "from the date such area was designated nonattainment under section 7407(d) of this title" and for the phrase "from the date of designation as nonattainment".

(July 14, 1955, ch. 360, title I, §179, as added Pub. L. 101–549, title I, §102(g), Nov. 15, 1990, 104 Stat. 2420.)

§7509a. International border areas

(a) Implementation plans and revisions

Notwithstanding any other provision of law, an implementation plan or plan revision required under this chapter shall be approved by the Administrator if—

(1) such plan or revision meets all the requirements applicable to it under the 1 chapter other than a requirement that such plan or revision demonstrate attainment and maintenance of the relevant national ambient air quality standards by the attainment date specified under the applicable provision of this chapter, or in a regulation promulgated under such provision, and

(2) the submitting State establishes to the satisfaction of the Administrator that the implementation plan of such State would be adequate to attain and maintain the relevant national ambient air quality standards by the attainment date specified under the applicable provision of this chapter, or in a regulation promulgated under such provision, but for emissions emanating from outside of the United States.

(b) Attainment of ozone levels

Notwithstanding any other provision of law, any State that establishes to the satisfaction of the Administrator that, with respect to an ozone nonattainment area in such State, such State would have attained the national ambient air quality standard for ozone by the applicable attainment date, but for emissions emanating from outside of the United States, shall not be subject to the provisions of section 7511(a)(2) or (5) of this title or section 7511d of this title.

(c) Attainment of carbon monoxide levels

Notwithstanding any other provision of law, any State that establishes to the satisfaction of the Administrator, with respect to a carbon monoxide nonattainment area in such State, that such State has attained the national ambient air quality standard for carbon monoxide by the applicable attainment date, but for emissions emanating from outside of the United States, shall not be subject to the provisions of section 7512(b)(2) or (9) 2 of this title.

(d) Attainment of PM–10 levels

Notwithstanding any other provision of law, any State that establishes to the satisfaction of the Administrator that, with respect to a PM–10 nonattainment area in such State, such State would have attained the national ambient air quality standard for carbon monoxide by the applicable attainment date, but for emissions emanating from outside the United States, shall not be subject to the provisions of section 7513(b)(2) of this title.

(July 14, 1955, ch. 360, title I, §179B, as added Pub. L. 101–549, title VIII, §818, Nov. 15, 1990, 104 Stat. 2697.)


Statutory Notes and Related Subsidiaries

Establishment of Program To Monitor and Improve Air Quality in Regions Along Border Between United States and Mexico

Pub. L. 101–549, title VIII, §815, Nov. 15, 1990, 104 Stat. 2693, provided that the Administrator of the Environmental Protection Agency was authorized, in cooperation with the Department of State and the affected border States, to negotiate with representatives of Mexico to authorize a program, not to extend beyond July 1, 1995, to monitor and improve air quality in regions along the border between the United States and Mexico, with requirements for monitoring, remediation, annual reports, and funding and personnel.

1 So in original. Probably should be "this".

2 So in original. Section 7512(b) of this title does not contain a par. (9).

subpart 2—additional provisions for ozone nonattainment areas

§7511. Classifications and attainment dates

(a) Classification and attainment dates for 1989 nonattainment areas

(1) Each area designated nonattainment for ozone pursuant to section 7407(d) of this title shall be classified at the time of such designation, under table 1, by operation of law, as a Marginal Area, a Moderate Area, a Serious Area, a Severe Area, or an Extreme Area based on the design value for the area. The design value shall be calculated according to the interpretation methodology issued by the Administrator most recently before November 15, 1990. For each area classified under this subsection, the primary standard attainment date for ozone shall be as expeditiously as practicable but not later than the date provided in table 1.

TABLE 1
Area classDesign value*Primary standard

attainment date**

Marginal 0.121 up to 0.138 3 years after November 15, 1990
Moderate 0.138 up to 0.160 6 years after November 15, 1990
Serious 0.160 up to 0.180 9 years after November 15, 1990
Severe 0.180 up to 0.280 15 years after November 15, 1990
Extreme 0.280 and above 20 years after November 15, 1990

*The design value is measured in parts per million (ppm).

**The primary standard attainment date is measured from November 15, 1990.

(2) Notwithstanding table 1, in the case of a severe area with a 1988 ozone design value between 0.190 and 0.280 ppm, the attainment date shall be 17 years (in lieu of 15 years) after November 15, 1990.

(3) At the time of publication of the notice under section 7407(d)(4) of this title (relating to area designations) for each ozone nonattainment area, the Administrator shall publish a notice announcing the classification of such ozone nonattainment area. The provisions of section 7502(a)(1)(B) of this title (relating to lack of notice and comment and judicial review) shall apply to such classification.

(4) If an area classified under paragraph (1) (Table 1) would have been classified in another category if the design value in the area were 5 percent greater or 5 percent less than the level on which such classification was based, the Administrator may, in the Administrator's discretion, within 90 days after the initial classification, by the procedure required under paragraph (3), adjust the classification to place the area in such other category. In making such adjustment, the Administrator may consider the number of exceedances of the national primary ambient air quality standard for ozone in the area, the level of pollution transport between the area and other affected areas, including both intrastate and interstate transport, and the mix of sources and air pollutants in the area.

(5) Upon application by any State, the Administrator may extend for 1 additional year (hereinafter referred to as the "Extension Year") the date specified in table 1 of paragraph (1) of this subsection if—

(A) the State has complied with all requirements and commitments pertaining to the area in the applicable implementation plan, and

(B) no more than 1 exceedance of the national ambient air quality standard level for ozone has occurred in the area in the year preceding the Extension Year.


No more than 2 one-year extensions may be issued under this paragraph for a single nonattainment area.

(b) New designations and reclassifications

(1) New designations to nonattainment

Any area that is designated attainment or unclassifiable for ozone under section 7407(d)(4) of this title, and that is subsequently redesignated to nonattainment for ozone under section 7407(d)(3) of this title, shall, at the time of the redesignation, be classified by operation of law in accordance with table 1 under subsection (a). Upon its classification, the area shall be subject to the same requirements under section 7410 of this title, subpart 1 of this part, and this subpart that would have applied had the area been so classified at the time of the notice under subsection (a)(3), except that any absolute, fixed date applicable in connection with any such requirement is extended by operation of law by a period equal to the length of time between November 15, 1990, and the date the area is classified under this paragraph.

(2) Reclassification upon failure to attain

(A) Within 6 months following the applicable attainment date (including any extension thereof) for an ozone nonattainment area, the Administrator shall determine, based on the area's design value (as of the attainment date), whether the area attained the standard by that date. Except for any Severe or Extreme area, any area that the Administrator finds has not attained the standard by that date shall be reclassified by operation of law in accordance with table 1 of subsection (a) to the higher of—

(i) the next higher classification for the area, or

(ii) the classification applicable to the area's design value as determined at the time of the notice required under subparagraph (B).


No area shall be reclassified as Extreme under clause (ii).

(B) The Administrator shall publish a notice in the Federal Register, no later than 6 months following the attainment date, identifying each area that the Administrator has determined under subparagraph (A) as having failed to attain and identifying the reclassification, if any, described under subparagraph (A).

(3) Voluntary reclassification

The Administrator shall grant the request of any State to reclassify a nonattainment area in that State in accordance with table 1 of subsection (a) to a higher classification. The Administrator shall publish a notice in the Federal Register of any such request and of action by the Administrator granting the request.

(4) Failure of Severe Areas to attain standard

(A) If any Severe Area fails to achieve the national primary ambient air quality standard for ozone by the applicable attainment date (including any extension thereof), the fee provisions under section 7511d of this title shall apply within the area, the percent reduction requirements of section 7511a(c)(2)(B) and (C) of this title (relating to reasonable further progress demonstration and NOx control) shall continue to apply to the area, and the State shall demonstrate that such percent reduction has been achieved in each 3-year interval after such failure until the standard is attained. Any failure to make such a demonstration shall be subject to the sanctions provided under this part.

(B) In addition to the requirements of subparagraph (A), if the ozone design value for a Severe Area referred to in subparagraph (A) is above 0.140 ppm for the year of the applicable attainment date, or if the area has failed to achieve its most recent milestone under section 7511a(g) of this title, the new source review requirements applicable under this subpart in Extreme Areas shall apply in the area and the term 1 "major source" and "major stationary source" shall have the same meaning as in Extreme Areas.

(C) In addition to the requirements of subparagraph (A) for those areas referred to in subparagraph (A) and not covered by subparagraph (B), the provisions referred to in subparagraph (B) shall apply after 3 years from the applicable attainment date unless the area has attained the standard by the end of such 3-year period.

(D) If, after November 15, 1990, the Administrator modifies the method of determining compliance with the national primary ambient air quality standard, a design value or other indicator comparable to 0.140 in terms of its relationship to the standard shall be used in lieu of 0.140 for purposes of applying the provisions of subparagraphs (B) and (C).

(c) References to terms

(1) Any reference in this subpart to a "Marginal Area", a "Moderate Area", a "Serious Area", a "Severe Area", or an "Extreme Area" shall be considered a reference to a Marginal Area, a Moderate Area, a Serious Area, a Severe Area, or an Extreme Area as respectively classified under this section.

(2) Any reference in this subpart to "next higher classification" or comparable terms shall be considered a reference to the classification related to the next higher set of design values in table 1.

(July 14, 1955, ch. 360, title I, §181, as added Pub. L. 101–549, title I, §103, Nov. 15, 1990, 104 Stat. 2423.)


Statutory Notes and Related Subsidiaries

Exemptions for Stripper Wells

Pub. L. 101–549, title VIII, §819, Nov. 15, 1990, 104 Stat. 2698, provided that: "Notwithstanding any other provision of law, the amendments to the Clean Air Act made by section 103 of the Clean Air Act Amendments of 1990 [enacting this section and sections 7511a to 7511f of this title] (relating to additional provisions for ozone nonattainment areas), by section 104 of such amendments [enacting sections 7512 and 7512a of this title] (relating to additional provisions for carbon monoxide nonattainment areas), by section 105 of such amendments [enacting sections 7513 to 7513b of this title and amending section 7476 of this title] (relating to additional provisions for PM–10 nonattainment areas), and by section 106 of such amendments [enacting sections 7514 and 7514a of this title] (relating to additional provisions for areas designated as nonattainment for sulfur oxides, nitrogen dioxide, and lead) shall not apply with respect to the production of and equipment used in the exploration, production, development, storage or processing of—

"(1) oil from a stripper well property, within the meaning of the June 1979 energy regulations (within the meaning of section 4996(b)(7) of the Internal Revenue Code of 1986 [26 U.S.C. 4996(b)(7)], as in effect before the repeal of such section); and

"(2) stripper well natural gas, as defined in section 108(b) of the Natural Gas Policy Act of 1978 (15 U.S.C. 3318(b)).[,]

except to the extent that provisions of such amendments cover areas designated as Serious pursuant to part D of title I of the Clean Air Act [this part] and having a population of 350,000 or more, or areas designated as Severe or Extreme pursuant to such part D."

1 So in original. Probably should be "terms".

§7511a. Plan submissions and requirements

(a) Marginal Areas

Each State in which all or part of a Marginal Area is located shall, with respect to the Marginal Area (or portion thereof, to the extent specified in this subsection), submit to the Administrator the State implementation plan revisions (including the plan items) described under this subsection except to the extent the State has made such submissions as of November 15, 1990.

(1) Inventory

Within 2 years after November 15, 1990, the State shall submit a comprehensive, accurate, current inventory of actual emissions from all sources, as described in section 7502(c)(3) of this title, in accordance with guidance provided by the Administrator.

(2) Corrections to the State implementation plan

Within the periods prescribed in this paragraph, the State shall submit a revision to the State implementation plan that meets the following requirements—

(A) Reasonably available control technology corrections

For any Marginal Area (or, within the Administrator's discretion, portion thereof) the State shall submit, within 6 months of the date of classification under section 7511(a) of this title, a revision that includes such provisions to correct requirements in (or add requirements to) the plan concerning reasonably available control technology as were required under section 7502(b) of this title (as in effect immediately before November 15, 1990), as interpreted in guidance issued by the Administrator under section 7408 of this title before November 15, 1990.

(B) Savings clause for vehicle inspection and maintenance

(i) For any Marginal Area (or, within the Administrator's discretion, portion thereof), the plan for which already includes, or was required by section 7502(b)(11)(B) of this title (as in effect immediately before November 15, 1990) to have included, a specific schedule for implementation of a vehicle emission control inspection and maintenance program, the State shall submit, immediately after November 15, 1990, a revision that includes any provisions necessary to provide for a vehicle inspection and maintenance program of no less stringency than that of either the program defined in House Report Numbered 95–294, 95th Congress, 1st Session, 281–291 (1977) as interpreted in guidance of the Administrator issued pursuant to section 7502(b)(11)(B) of this title (as in effect immediately before November 15, 1990) or the program already included in the plan, whichever is more stringent.

(ii) Within 12 months after November 15, 1990, the Administrator shall review, revise, update, and republish in the Federal Register the guidance for the States for motor vehicle inspection and maintenance programs required by this chapter, taking into consideration the Administrator's investigations and audits of such program. The guidance shall, at a minimum, cover the frequency of inspections, the types of vehicles to be inspected (which shall include leased vehicles that are registered in the nonattainment area), vehicle maintenance by owners and operators, audits by the State, the test method and measures, including whether centralized or decentralized, inspection methods and procedures, quality of inspection, components covered, assurance that a vehicle subject to a recall notice from a manufacturer has complied with that notice, and effective implementation and enforcement, including ensuring that any retesting of a vehicle after a failure shall include proof of corrective action and providing for denial of vehicle registration in the case of tampering or misfueling. The guidance which shall be incorporated in the applicable State implementation plans by the States shall provide the States with continued reasonable flexibility to fashion effective, reasonable, and fair programs for the affected consumer. No later than 2 years after the Administrator promulgates regulations under section 7521(m)(3) of this title (relating to emission control diagnostics), the State shall submit a revision to such program to meet any requirements that the Administrator may prescribe under that section.

(C) Permit programs

Within 2 years after November 15, 1990, the State shall submit a revision that includes each of the following:

(i) Provisions to require permits, in accordance with sections 7502(c)(5) and 7503 of this title, for the construction and operation of each new or modified major stationary source (with respect to ozone) to be located in the area.

(ii) Provisions to correct requirements in (or add requirements to) the plan concerning permit programs as were required under section 7502(b)(6) of this title (as in effect immediately before November 15, 1990), as interpreted in regulations of the Administrator promulgated as of November 15, 1990.

(3) Periodic inventory

(A) General requirement

No later than the end of each 3-year period after submission of the inventory under paragraph (1) until the area is redesignated to attainment, the State shall submit a revised inventory meeting the requirements of subsection (a)(1).

(B) Emissions statements

(i) Within 2 years after November 15, 1990, the State shall submit a revision to the State implementation plan to require that the owner or operator of each stationary source of oxides of nitrogen or volatile organic compounds provide the State with a statement, in such form as the Administrator may prescribe (or accept an equivalent alternative developed by the State), for classes or categories of sources, showing the actual emissions of oxides of nitrogen and volatile organic compounds from that source. The first such statement shall be submitted within 3 years after November 15, 1990. Subsequent statements shall be submitted at least every year thereafter. The statement shall contain a certification that the information contained in the statement is accurate to the best knowledge of the individual certifying the statement.

(ii) The State may waive the application of clause (i) to any class or category of stationary sources which emit less than 25 tons per year of volatile organic compounds or oxides of nitrogen if the State, in its submissions under subparagraphs 1 (1) or (3)(A), provides an inventory of emissions from such class or category of sources, based on the use of the emission factors established by the Administrator or other methods acceptable to the Administrator.

(4) General offset requirement

For purposes of satisfying the emission offset requirements of this part, the ratio of total emission reductions of volatile organic compounds to total increased emissions of such air pollutant shall be at least 1.1 to 1.


The Administrator may, in the Administrator's discretion, require States to submit a schedule for submitting any of the revisions or other items required under this subsection. The requirements of this subsection shall apply in lieu of any requirement that the State submit a demonstration that the applicable implementation plan provides for attainment of the ozone standard by the applicable attainment date in any Marginal Area. Section 7502(c)(9) of this title (relating to contingency measures) shall not apply to Marginal Areas.

(b) Moderate Areas

Each State in which all or part of a Moderate Area is located shall, with respect to the Moderate Area, make the submissions described under subsection (a) of this section (relating to Marginal Areas), and shall also submit the revisions to the applicable implementation plan described under this subsection.

(1) Plan provisions for reasonable further progress

(A) General rule

(i) By no later than 3 years after November 15, 1990, the State shall submit a revision to the applicable implementation plan to provide for volatile organic compound emission reductions, within 6 years after November 15, 1990, of at least 15 percent from baseline emissions, accounting for any growth in emissions after 1990. Such plan shall provide for such specific annual reductions in emissions of volatile organic compounds and oxides of nitrogen as necessary to attain the national primary ambient air quality standard for ozone by the attainment date applicable under this chapter. This subparagraph shall not apply in the case of oxides of nitrogen for those areas for which the Administrator determines (when the Administrator approves the plan or plan revision) that additional reductions of oxides of nitrogen would not contribute to attainment.

(ii) A percentage less than 15 percent may be used for purposes of clause (i) in the case of any State which demonstrates to the satisfaction of the Administrator that—

(I) new source review provisions are applicable in the nonattainment areas in the same manner and to the same extent as required under subsection (e) in the case of Extreme Areas (with the exception that, in applying such provisions, the terms "major source" and "major stationary source" shall include (in addition to the sources described in section 7602 of this title) any stationary source or group of sources located within a contiguous area and under common control that emits, or has the potential to emit, at least 5 tons per year of volatile organic compounds);

(II) reasonably available control technology is required for all existing major sources (as defined in subclause (I)); and

(III) the plan reflecting a lesser percentage than 15 percent includes all measures that can feasibly be implemented in the area, in light of technological achievability.


To qualify for a lesser percentage under this clause, a State must demonstrate to the satisfaction of the Administrator that the plan for the area includes the measures that are achieved in practice by sources in the same source category in nonattainment areas of the next higher category.

(B) Baseline emissions

For purposes of subparagraph (A), the term "baseline emissions" means the total amount of actual VOC or NOx emissions from all anthropogenic sources in the area during the calendar year 1990, excluding emissions that would be eliminated under the regulations described in clauses (i) and (ii) of subparagraph (D).

(C) General rule for creditability of reductions

Except as provided under subparagraph (D), emissions reductions are creditable toward the 15 percent required under subparagraph (A) to the extent they have actually occurred, as of 6 years after November 15, 1990, from the implementation of measures required under the applicable implementation plan, rules promulgated by the Administrator, or a permit under subchapter V.

(D) Limits on creditability of reductions

Emission reductions from the following measures are not creditable toward the 15 percent reductions required under subparagraph (A):

(i) Any measure relating to motor vehicle exhaust or evaporative emissions promulgated by the Administrator by January 1, 1990.

(ii) Regulations concerning Reid Vapor Pressure promulgated by the Administrator by November 15, 1990, or required to be promulgated under section 7545(h) of this title.

(iii) Measures required under subsection (a)(2)(A) (concerning corrections to implementation plans prescribed under guidance by the Administrator).

(iv) Measures required under subsection (a)(2)(B) to be submitted immediately after November 15, 1990 (concerning corrections to motor vehicle inspection and maintenance programs).

(2) Reasonably available control technology

The State shall submit a revision to the applicable implementation plan to include provisions to require the implementation of reasonably available control technology under section 7502(c)(1) of this title with respect to each of the following:

(A) Each category of VOC sources in the area covered by a CTG document issued by the Administrator between November 15, 1990, and the date of attainment.

(B) All VOC sources in the area covered by any CTG issued before November 15, 1990.

(C) All other major stationary sources of VOCs that are located in the area.


Each revision described in subparagraph (A) shall be submitted within the period set forth by the Administrator in issuing the relevant CTG document. The revisions with respect to sources described in subparagraphs (B) and (C) shall be submitted by 2 years after November 15, 1990, and shall provide for the implementation of the required measures as expeditiously as practicable but no later than May 31, 1995.

(3) Gasoline vapor recovery

(A) General rule

Not later than 2 years after November 15, 1990, the State shall submit a revision to the applicable implementation plan to require all owners or operators of gasoline dispensing systems to install and operate, by the date prescribed under subparagraph (B), a system for gasoline vapor recovery of emissions from the fueling of motor vehicles. The Administrator shall issue guidance as appropriate as to the effectiveness of such system. This subparagraph shall apply only to facilities which sell more than 10,000 gallons of gasoline per month (50,000 gallons per month in the case of an independent small business marketer of gasoline as defined in section 7625–1 2 of this title).

(B) Effective date

The date required under subparagraph (A) shall be—

(i) 6 months after the adoption date, in the case of gasoline dispensing facilities for which construction commenced after November 15, 1990;

(ii) one year after the adoption date, in the case of gasoline dispensing facilities which dispense at least 100,000 gallons of gasoline per month, based on average monthly sales for the 2-year period before the adoption date; or

(iii) 2 years after the adoption date, in the case of all other gasoline dispensing facilities.


Any gasoline dispensing facility described under both clause (i) and clause (ii) shall meet the requirements of clause (i).

(C) Reference to terms

For purposes of this paragraph, any reference to the term "adoption date" shall be considered a reference to the date of adoption by the State of requirements for the installation and operation of a system for gasoline vapor recovery of emissions from the fueling of motor vehicles.

(4) Motor vehicle inspection and maintenance

For all Moderate Areas, the State shall submit, immediately after November 15, 1990, a revision to the applicable implementation plan that includes provisions necessary to provide for a vehicle inspection and maintenance program as described in subsection (a)(2)(B) (without regard to whether or not the area was required by section 7502(b)(11)(B) of this title (as in effect immediately before November 15, 1990) to have included a specific schedule for implementation of such a program).

(5) General offset requirement

For purposes of satisfying the emission offset requirements of this part, the ratio of total emission reductions of volatile organic compounds to total increase 3 emissions of such air pollutant shall be at least 1.15 to 1.

(c) Serious Areas

Except as otherwise specified in paragraph (4), each State in which all or part of a Serious Area is located shall, with respect to the Serious Area (or portion thereof, to the extent specified in this subsection), make the submissions described under subsection (b) (relating to Moderate Areas), and shall also submit the revisions to the applicable implementation plan (including the plan items) described under this subsection. For any Serious Area, the terms "major source" and "major stationary source" include (in addition to the sources described in section 7602 of this title) any stationary source or group of sources located within a contiguous area and under common control that emits, or has the potential to emit, at least 50 tons per year of volatile organic compounds.

(1) Enhanced monitoring

In order to obtain more comprehensive and representative data on ozone air pollution, not later than 18 months after November 15, 1990, the Administrator shall promulgate rules, after notice and public comment, for enhanced monitoring of ozone, oxides of nitrogen, and volatile organic compounds. The rules shall, among other things, cover the location and maintenance of monitors. Immediately following the promulgation of rules by the Administrator relating to enhanced monitoring, the State shall commence such actions as may be necessary to adopt and implement a program based on such rules, to improve monitoring for ambient concentrations of ozone, oxides of nitrogen and volatile organic compounds and to improve monitoring of emissions of oxides of nitrogen and volatile organic compounds. Each State implementation plan for the area shall contain measures to improve the ambient monitoring of such air pollutants.

(2) Attainment and reasonable further progress demonstrations

Within 4 years after November 15, 1990, the State shall submit a revision to the applicable implementation plan that includes each of the following:

(A) Attainment demonstration

A demonstration that the plan, as revised, will provide for attainment of the ozone national ambient air quality standard by the applicable attainment date. This attainment demonstration must be based on photochemical grid modeling or any other analytical method determined by the Administrator, in the Administrator's discretion, to be at least as effective.

(B) Reasonable further progress demonstration

A demonstration that the plan, as revised, will result in VOC emissions reductions from the baseline emissions described in subsection (b)(1)(B) equal to the following amount averaged over each consecutive 3-year period beginning 6 years after November 15, 1990, until the attainment date:

(i) at least 3 percent of baseline emissions each year; or

(ii) an amount less than 3 percent of such baseline emissions each year, if the State demonstrates to the satisfaction of the Administrator that the plan reflecting such lesser amount includes all measures that can feasibly be implemented in the area, in light of technological achievability.


To lessen the 3 percent requirement under clause (ii), a State must demonstrate to the satisfaction of the Administrator that the plan for the area includes the measures that are achieved in practice by sources in the same source category in nonattainment areas of the next higher classification. Any determination to lessen the 3 percent requirement shall be reviewed at each milestone under subsection (g) and revised to reflect such new measures (if any) achieved in practice by sources in the same category in any State, allowing a reasonable time to implement such measures. The emission reductions described in this subparagraph shall be calculated in accordance with subsection (b)(1)(C) and (D) (concerning creditability of reductions). The reductions creditable for the period beginning 6 years after November 15, 1990, shall include reductions that occurred before such period, computed in accordance with subsection (b)(1), that exceed the 15-percent amount of reductions required under subsection (b)(1)(A).

(C) NOx control

The revision may contain, in lieu of the demonstration required under subparagraph (B), a demonstration to the satisfaction of the Administrator that the applicable implementation plan, as revised, provides for reductions of emissions of VOC's and oxides of nitrogen (calculated according to the creditability provisions of subsection (b)(1)(C) and (D)), that would result in a reduction in ozone concentrations at least equivalent to that which would result from the amount of VOC emission reductions required under subparagraph (B). Within 1 year after November 15, 1990, the Administrator shall issue guidance concerning the conditions under which NOx control may be substituted for VOC control or may be combined with VOC control in order to maximize the reduction in ozone air pollution. In accord with such guidance, a lesser percentage of VOCs may be accepted as an adequate demonstration for purposes of this subsection.

(3) Enhanced vehicle inspection and maintenance program

(A) Requirement for submission

Within 2 years after November 15, 1990, the State shall submit a revision to the applicable implementation plan to provide for an enhanced program to reduce hydrocarbon emissions and NOx emissions from in-use motor vehicles registered in each urbanized area (in the nonattainment area), as defined by the Bureau of the Census, with a 1980 population of 200,000 or more.

(B) Effective date of State programs; guidance

The State program required under subparagraph (A) shall take effect no later than 2 years from November 15, 1990, and shall comply in all respects with guidance published in the Federal Register (and from time to time revised) by the Administrator for enhanced vehicle inspection and maintenance programs. Such guidance shall include—

(i) a performance standard achievable by a program combining emission testing, including on-road emission testing, with inspection to detect tampering with emission control devices and misfueling for all light-duty vehicles and all light-duty trucks subject to standards under section 7521 of this title; and

(ii) program administration features necessary to reasonably assure that adequate management resources, tools, and practices are in place to attain and maintain the performance standard.


Compliance with the performance standard under clause (i) shall be determined using a method to be established by the Administrator.

(C) State program

The State program required under subparagraph (A) shall include, at a minimum, each of the following elements—

(i) Computerized emission analyzers, including on-road testing devices.

(ii) No waivers for vehicles and parts covered by the emission control performance warranty as provided for in section 7541(b) of this title unless a warranty remedy has been denied in writing, or for tampering-related repairs.

(iii) In view of the air quality purpose of the program, if, for any vehicle, waivers are permitted for emissions-related repairs not covered by warranty, an expenditure to qualify for the waiver of an amount of $450 or more for such repairs (adjusted annually as determined by the Administrator on the basis of the Consumer Price Index in the same manner as provided in subchapter V).

(iv) Enforcement through denial of vehicle registration (except for any program in operation before November 15, 1990, whose enforcement mechanism is demonstrated to the Administrator to be more effective than the applicable vehicle registration program in assuring that noncomplying vehicles are not operated on public roads).

(v) Annual emission testing and necessary adjustment, repair, and maintenance, unless the State demonstrates to the satisfaction of the Administrator that a biennial inspection, in combination with other features of the program which exceed the requirements of this chapter, will result in emission reductions which equal or exceed the reductions which can be obtained through such annual inspections.

(vi) Operation of the program on a centralized basis, unless the State demonstrates to the satisfaction of the Administrator that a decentralized program will be equally effective. An electronically connected testing system, a licensing system, or other measures (or any combination thereof) may be considered, in accordance with criteria established by the Administrator, as equally effective for such purposes.

(vii) Inspection of emission control diagnostic systems and the maintenance or repair of malfunctions or system deterioration identified by or affecting such diagnostics systems.


Each State shall biennially prepare a report to the Administrator which assesses the emission reductions achieved by the program required under this paragraph based on data collected during inspection and repair of vehicles. The methods used to assess the emission reductions shall be those established by the Administrator.

(4) Clean-fuel vehicle programs

(A) Except to the extent that substitute provisions have been approved by the Administrator under subparagraph (B), the State shall submit to the Administrator, within 42 months of November 15, 1990, a revision to the applicable implementation plan for each area described under part C of subchapter II to include such measures as may be necessary to ensure the effectiveness of the applicable provisions of the clean-fuel vehicle program prescribed under part C of subchapter II, including all measures necessary to make the use of clean alternative fuels in clean-fuel vehicles (as defined in part C of subchapter II) economic from the standpoint of vehicle owners. Such a revision shall also be submitted for each area that opts into the clean fuel-vehicle program as provided in part C of subchapter II.

(B) The Administrator shall approve, as a substitute for all or a portion of the clean-fuel vehicle program prescribed under part C of subchapter II, any revision to the relevant applicable implementation plan that in the Administrator's judgment will achieve long-term reductions in ozone-producing and toxic air emissions equal to those achieved under part C of subchapter II, or the percentage thereof attributable to the portion of the clean-fuel vehicle program for which the revision is to substitute. The Administrator may approve such revision only if it consists exclusively of provisions other than those required under this chapter for the area. Any State seeking approval of such revision must submit the revision to the Administrator within 24 months of November 15, 1990. The Administrator shall approve or disapprove any such revision within 30 months of November 15, 1990. The Administrator shall publish the revision submitted by a State in the Federal Register upon receipt. Such notice shall constitute a notice of proposed rulemaking on whether or not to approve such revision and shall be deemed to comply with the requirements concerning notices of proposed rulemaking contained in sections 553 through 557 of title 5 (related to notice and comment). Where the Administrator approves such revision for any area, the State need not submit the revision required by subparagraph (A) for the area with respect to the portions of the Federal clean-fuel vehicle program for which the Administrator has approved the revision as a substitute.

(C) If the Administrator determines, under section 7509 of this title, that the State has failed to submit any portion of the program required under subparagraph (A), then, in addition to any sanctions available under section 7509 of this title, the State may not receive credit, in any demonstration of attainment or reasonable further progress for the area, for any emission reductions from implementation of the corresponding aspects of the Federal clean-fuel vehicle requirements established in part C of subchapter II.

(5) Transportation control

(A) 4 Beginning 6 years after November 15, 1990, and each third year thereafter, the State shall submit a demonstration as to whether current aggregate vehicle mileage, aggregate vehicle emissions, congestion levels, and other relevant parameters are consistent with those used for the area's demonstration of attainment. Where such parameters and emissions levels exceed the levels projected for purposes of the area's attainment demonstration, the State shall within 18 months develop and submit a revision of the applicable implementation plan that includes a transportation control measures program consisting of measures from, but not limited to, section 7408(f) of this title that will reduce emissions to levels that are consistent with emission levels projected in such demonstration. In considering such measures, the State should ensure adequate access to downtown, other commercial, and residential areas and should avoid measures that increase or relocate emissions and congestion rather than reduce them. Such revision shall be developed in accordance with guidance issued by the Administrator pursuant to section 7408(e) of this title and with the requirements of section 7504(b) of this title and shall include implementation and funding schedules that achieve expeditious emissions reductions in accordance with implementation plan projections.

(6) De minimis rule

The new source review provisions under this part shall ensure that increased emissions of volatile organic compounds resulting from any physical change in, or change in the method of operation of, a stationary source located in the area shall not be considered de minimis for purposes of determining the applicability of the permit requirements established by this chapter unless the increase in net emissions of such air pollutant from such source does not exceed 25 tons when aggregated with all other net increases in emissions from the source over any period of 5 consecutive calendar years which includes the calendar year in which such increase occurred.

(7) Special rule for modifications of sources emitting less than 100 tons

In the case of any major stationary source of volatile organic compounds located in the area (other than a source which emits or has the potential to emit 100 tons or more of volatile organic compounds per year), whenever any change (as described in section 7411(a)(4) of this title) at that source results in any increase (other than a de minimis increase) in emissions of volatile organic compounds from any discrete operation, unit, or other pollutant emitting activity at the source, such increase shall be considered a modification for purposes of section 7502(c)(5) of this title and section 7503(a) of this title, except that such increase shall not be considered a modification for such purposes if the owner or operator of the source elects to offset the increase by a greater reduction in emissions of volatile organic compounds concerned from other operations, units, or activities within the source at an internal offset ratio of at least 1.3 to 1. If the owner or operator does not make such election, such change shall be considered a modification for such purposes, but in applying section 7503(a)(2) of this title in the case of any such modification, the best available control technology (BACT), as defined in section 7479 of this title, shall be substituted for the lowest achievable emission rate (LAER). The Administrator shall establish and publish policies and procedures for implementing the provisions of this paragraph.

(8) Special rule for modifications of sources emitting 100 tons or more

In the case of any major stationary source of volatile organic compounds located in the area which emits or has the potential to emit 100 tons or more of volatile organic compounds per year, whenever any change (as described in section 7411(a)(4) of this title) at that source results in any increase (other than a de minimis increase) in emissions of volatile organic compounds from any discrete operation, unit, or other pollutant emitting activity at the source, such increase shall be considered a modification for purposes of section 7502(c)(5) of this title and section 7503(a) of this title, except that if the owner or operator of the source elects to offset the increase by a greater reduction in emissions of volatile organic compounds from other operations, units, or activities within the source at an internal offset ratio of at least 1.3 to 1, the requirements of section 7503(a)(2) of this title (concerning the lowest achievable emission rate (LAER)) shall not apply.

(9) Contingency provisions

In addition to the contingency provisions required under section 7502(c)(9) of this title, the plan revision shall provide for the implementation of specific measures to be undertaken if the area fails to meet any applicable milestone. Such measures shall be included in the plan revision as contingency measures to take effect without further action by the State or the Administrator upon a failure by the State to meet the applicable milestone.

(10) General offset requirement

For purposes of satisfying the emission offset requirements of this part, the ratio of total emission reductions of volatile organic compounds to total increase emissions of such air pollutant shall be at least 1.2 to 1.


Any reference to "attainment date" in subsection (b), which is incorporated by reference into this subsection, shall refer to the attainment date for serious areas.

(d) Severe Areas

Each State in which all or part of a Severe Area is located shall, with respect to the Severe Area, make the submissions described under subsection (c) (relating to Serious Areas), and shall also submit the revisions to the applicable implementation plan (including the plan items) described under this subsection. For any Severe Area, the terms "major source" and "major stationary source" include (in addition to the sources described in section 7602 of this title) any stationary source or group of sources located within a contiguous area and under common control that emits, or has the potential to emit, at least 25 tons per year of volatile organic compounds.

(1) Vehicle miles traveled

(A) Within 2 years after November 15, 1990, the State shall submit a revision that identifies and adopts specific enforceable transportation control strategies and transportation control measures to offset any growth in emissions from growth in vehicle miles traveled or numbers of vehicle trips in such area and to attain reduction in motor vehicle emissions as necessary, in combination with other emission reduction requirements of this subpart, to comply with the requirements of subsection 5 (b)(2)(B) and (c)(2)(B) (pertaining to periodic emissions reduction requirements). The State shall consider measures specified in section 7408(f) of this title, and choose from among and implement such measures as necessary to demonstrate attainment with the national ambient air quality standards; in considering such measures, the State should ensure adequate access to downtown, other commercial, and residential areas and should avoid measures that increase or relocate emissions and congestion rather than reduce them.

(B) The State may also, in its discretion, submit a revision at any time requiring employers in such area to implement programs to reduce work-related vehicle trips and miles travelled by employees. Such revision shall be developed in accordance with guidance issued by the Administrator pursuant to section 7408(f) of this title and may require that employers in such area increase average passenger occupancy per vehicle in commuting trips between home and the workplace during peak travel periods. The guidance of the Administrator may specify average vehicle occupancy rates which vary for locations within a nonattainment area (suburban, center city, business district) or among nonattainment areas reflecting existing occupancy rates and the availability of high occupancy modes. Any State required to submit a revision under this subparagraph (as in effect before December 23, 1995) containing provisions requiring employers to reduce work-related vehicle trips and miles travelled by employees may, in accordance with State law, remove such provisions from the implementation plan, or withdraw its submission, if the State notifies the Administrator, in writing, that the State has undertaken, or will undertake, one or more alternative methods that will achieve emission reductions equivalent to those to be achieved by the removed or withdrawn provisions.

(2) Offset requirement

For purposes of satisfying the offset requirements pursuant to this part, the ratio of total emission reductions of VOCs to total increased emissions of such air pollutant shall be at least 1.3 to 1, except that if the State plan requires all existing major sources in the nonattainment area to use best available control technology (as defined in section 7479(3) of this title) for the control of volatile organic compounds, the ratio shall be at least 1.2 to 1.

(3) Enforcement under section 7511d

By December 31, 2000, the State shall submit a plan revision which includes the provisions required under section 7511d of this title.


Any reference to the term "attainment date" in subsection (b) or (c), which is incorporated by reference into this subsection (d), shall refer to the attainment date for Severe Areas.

(e) Extreme Areas

Each State in which all or part of an Extreme Area is located shall, with respect to the Extreme Area, make the submissions described under subsection (d) (relating to Severe Areas), and shall also submit the revisions to the applicable implementation plan (including the plan items) described under this subsection. The provisions of clause (ii) of subsection (c)(2)(B) (relating to reductions of less than 3 percent), the provisions of paragaphs 6 (6), (7) and (8) of subsection (c) (relating to de minimus 7 rule and modification of sources), and the provisions of clause (ii) of subsection (b)(1)(A) (relating to reductions of less than 15 percent) shall not apply in the case of an Extreme Area. For any Extreme Area, the terms "major source" and "major stationary source" includes 8 (in addition to the sources described in section 7602 of this title) any stationary source or group of sources located within a contiguous area and under common control that emits, or has the potential to emit, at least 10 tons per year of volatile organic compounds.

(1) Offset requirement

For purposes of satisfying the offset requirements pursuant to this part, the ratio of total emission reductions of VOCs to total increased emissions of such air pollutant shall be at least 1.5 to 1, except that if the State plan requires all existing major sources in the nonattainment area to use best available control technology (as defined in section 7479(3) of this title) for the control of volatile organic compounds, the ratio shall be at least 1.2 to 1.

(2) Modifications

Any change (as described in section 7411(a)(4) of this title) at a major stationary source which results in any increase in emissions from any discrete operation, unit, or other pollutant emitting activity at the source shall be considered a modification for purposes of section 7502(c)(5) of this title and section 7503(a) of this title, except that for purposes of complying with the offset requirement pursuant to section 7503(a)(1) of this title, any such increase shall not be considered a modification if the owner or operator of the source elects to offset the increase by a greater reduction in emissions of the air pollutant concerned from other discrete operations, units, or activities within the source at an internal offset ratio of at least 1.3 to 1. The offset requirements of this part shall not be applicable in Extreme Areas to a modification of an existing source if such modification consists of installation of equipment required to comply with the applicable implementation plan, permit, or this chapter.

(3) Use of clean fuels or advanced control technology

For Extreme Areas, a plan revision shall be submitted within 3 years after November 15, 1990, to require, effective 8 years after November 15, 1990, that each new, modified, and existing electric utility and industrial and commercial boiler which emits more than 25 tons per year of oxides of nitrogen—

(A) burn as its primary fuel natural gas, methanol, or ethanol (or a comparably low polluting fuel), or

(B) use advanced control technology (such as catalytic control technology or other comparably effective control methods) for reduction of emissions of oxides of nitrogen.


For purposes of this subsection, the term "primary fuel" means the fuel which is used 90 percent or more of the operating time. This paragraph shall not apply during any natural gas supply emergency (as defined in title III of the Natural Gas Policy Act of 1978 [15 U.S.C. 3361 et seq.]).

(4) Traffic control measures during heavy traffic hours

For Extreme Areas, each implementation plan revision under this subsection may contain provisions establishing traffic control measures applicable during heavy traffic hours to reduce the use of high polluting vehicles or heavy-duty vehicles, notwithstanding any other provision of law.

(5) New technologies

The Administrator may, in accordance with section 7410 of this title, approve provisions of an implementation plan for an Extreme Area which anticipate development of new control techniques or improvement of existing control technologies, and an attainment demonstration based on such provisions, if the State demonstrates to the satisfaction of the Administrator that—

(A) such provisions are not necessary to achieve the incremental emission reductions required during the first 10 years after November 15, 1990; and

(B) the State has submitted enforceable commitments to develop and adopt contingency measures to be implemented as set forth herein if the anticipated technologies do not achieve planned reductions.


Such contingency measures shall be submitted to the Administrator no later than 3 years before proposed implementation of the plan provisions and approved or disapproved by the Administrator in accordance with section 7410 of this title. The contingency measures shall be adequate to produce emission reductions sufficient, in conjunction with other approved plan provisions, to achieve the periodic emission reductions required by subsection (b)(1) or (c)(2) and attainment by the applicable dates. If the Administrator determines that an Extreme Area has failed to achieve an emission reduction requirement set forth in subsection (b)(1) or (c)(2), and that such failure is due in whole or part to an inability to fully implement provisions approved pursuant to this subsection, the Administrator shall require the State to implement the contingency measures to the extent necessary to assure compliance with subsections (b)(1) and (c)(2).


Any reference to the term "attainment date" in subsection (b), (c), or (d) which is incorporated by reference into this subsection, shall refer to the attainment date for Extreme Areas.

(f) NOx requirements

(1) The plan provisions required under this subpart for major stationary sources of volatile organic compounds shall also apply to major stationary sources (as defined in section 7602 of this title and subsections (c), (d), and (e) of this section) of oxides of nitrogen. This subsection shall not apply in the case of oxides of nitrogen for those sources for which the Administrator determines (when the Administrator approves a plan or plan revision) that net air quality benefits are greater in the absence of reductions of oxides of nitrogen from the sources concerned. This subsection shall also not apply in the case of oxides of nitrogen for—

(A) nonattainment areas not within an ozone transport region under section 7511c of this title, if the Administrator determines (when the Administrator approves a plan or plan revision) that additional reductions of oxides of nitrogen would not contribute to attainment of the national ambient air quality standard for ozone in the area, or

(B) nonattainment areas within such an ozone transport region if the Administrator determines (when the Administrator approves a plan or plan revision) that additional reductions of oxides of nitrogen would not produce net ozone air quality benefits in such region.


The Administrator shall, in the Administrator's determinations, consider the study required under section 7511f of this title.

(2)(A) If the Administrator determines that excess reductions in emissions of NOx would be achieved under paragraph (1), the Administrator may limit the application of paragraph (1) to the extent necessary to avoid achieving such excess reductions.

(B) For purposes of this paragraph, excess reductions in emissions of NOx are emission reductions for which the Administrator determines that net air quality benefits are greater in the absence of such reductions. Alternatively, for purposes of this paragraph, excess reductions in emissions of NOx are, for—

(i) nonattainment areas not within an ozone transport region under section 7511c of this title, emission reductions that the Administrator determines would not contribute to attainment of the national ambient air quality standard for ozone in the area, or

(ii) nonattainment areas within such ozone transport region, emission reductions that the Administrator determines would not produce net ozone air quality benefits in such region.


(3) At any time after the final report under section 7511f of this title is submitted to Congress, a person may petition the Administrator for a determination under paragraph (1) or (2) with respect to any nonattainment area or any ozone transport region under section 7511c of this title. The Administrator shall grant or deny such petition within 6 months after its filing with the Administrator.

(g) Milestones

(1) Reductions in emissions

6 years after November 15, 1990, and at intervals of every 3 years thereafter, the State shall determine whether each nonattainment area (other than an area classified as Marginal or Moderate) has achieved a reduction in emissions during the preceding intervals equivalent to the total emission reductions required to be achieved by the end of such interval pursuant to subsection (b)(1) and the corresponding requirements of subsections (c)(2)(B) and (C), (d), and (e). Such reduction shall be referred to in this section as an applicable milestone.

(2) Compliance demonstration

For each nonattainment area referred to in paragraph (1), not later than 90 days after the date on which an applicable milestone occurs (not including an attainment date on which a milestone occurs in cases where the standard has been attained), each State in which all or part of such area is located shall submit to the Administrator a demonstration that the milestone has been met. A demonstration under this paragraph shall be submitted in such form and manner, and shall contain such information and analysis, as the Administrator shall require, by rule. The Administrator shall determine whether or not a State's demonstration is adequate within 90 days after the Administrator's receipt of a demonstration which contains the information and analysis required by the Administrator.

(3) Serious and Severe Areas; State election

If a State fails to submit a demonstration under paragraph (2) for any Serious or Severe Area within the required period or if the Administrator determines that the area has not met any applicable milestone, the State shall elect, within 90 days after such failure or determination—

(A) to have the area reclassified to the next higher classification,

(B) to implement specific additional measures adequate, as determined by the Administrator, to meet the next milestone as provided in the applicable contingency plan, or

(C) to adopt an economic incentive program as described in paragraph (4).


If the State makes an election under subparagraph (B), the Administrator shall, within 90 days after the election, review such plan and shall, if the Administrator finds the contingency plan inadequate, require further measures necessary to meet such milestone. Once the State makes an election, it shall be deemed accepted by the Administrator as meeting the election requirement. If the State fails to make an election required under this paragraph within the required 90-day period or within 6 months thereafter, the area shall be reclassified to the next higher classification by operation of law at the expiration of such 6-month period. Within 12 months after the date required for the State to make an election, the State shall submit a revision of the applicable implementation plan for the area that meets the requirements of this paragraph. The Administrator shall review such plan revision and approve or disapprove the revision within 9 months after the date of its submission.

(4) Economic incentive program

(A) An economic incentive program under this paragraph shall be consistent with rules published by the Administrator and sufficient, in combination with other elements of the State plan, to achieve the next milestone. The State program may include a nondiscriminatory system, consistent with applicable law regarding interstate commerce, of State established emissions fees or a system of marketable permits, or a system of State fees on sale or manufacture of products the use of which contributes to ozone formation, or any combination of the foregoing or other similar measures. The program may also include incentives and requirements to reduce vehicle emissions and vehicle miles traveled in the area, including any of the transportation control measures identified in section 7408(f) of this title.

(B) Within 2 years after November 15, 1990, the Administrator shall publish rules for the programs to be adopted pursuant to subparagraph (A). Such rules shall include model plan provisions which may be adopted for reducing emissions from permitted stationary sources, area sources, and mobile sources. The guidelines shall require that any revenues generated by the plan provisions adopted pursuant to subparagraph (A) shall be used by the State for any of the following:

(i) Providing incentives for achieving emission reductions.

(ii) Providing assistance for the development of innovative technologies for the control of ozone air pollution and for the development of lower-polluting solvents and surface coatings. Such assistance shall not provide for the payment of more than 75 percent of either the costs of any project to develop such a technology or the costs of development of a lower-polluting solvent or surface coating.

(iii) Funding the administrative costs of State programs under this chapter. Not more than 50 percent of such revenues may be used for purposes of this clause.

(5) Extreme Areas

If a State fails to submit a demonstration under paragraph (2) for any Extreme Area within the required period, or if the Administrator determines that the area has not met any applicable milestone, the State shall, within 9 months after such failure or determination, submit a plan revision to implement an economic incentive program which meets the requirements of paragraph (4). The Administrator shall review such plan revision and approve or disapprove the revision within 9 months after the date of its submission.

(h) Rural transport areas

(1) Notwithstanding any other provision of section 7511 of this title or this section, a State containing an ozone nonattainment area that does not include, and is not adjacent to, any part of a Metropolitan Statistical Area or, where one exists, a Consolidated Metropolitan Statistical Area (as defined by the United States Bureau of the Census), which area is treated by the Administrator, in the Administrator's discretion, as a rural transport area within the meaning of paragraph (2), shall be treated by operation of law as satisfying the requirements of this section if it makes the submissions required under subsection (a) of this section (relating to marginal areas).

(2) The Administrator may treat an ozone nonattainment area as a rural transport area if the Administrator finds that sources of VOC (and, where the Administrator determines relevant, NOx) emissions within the area do not make a significant contribution to the ozone concentrations measured in the area or in other areas.

(i) Reclassified areas

Each State containing an ozone nonattainment area reclassified under section 7511(b)(2) of this title shall meet such requirements of subsections (b) through (d) of this section as may be applicable to the area as reclassified, according to the schedules prescribed in connection with such requirements, except that the Administrator may adjust any applicable deadlines (other than attainment dates) to the extent such adjustment is necessary or appropriate to assure consistency among the required submissions.

(j) Multi-State ozone nonattainment areas

(1) Coordination among States

Each State in which there is located a portion of a single ozone nonattainment area which covers more than one State (hereinafter in this section referred to as a "multi-State ozone nonattainment area") shall—

(A) take all reasonable steps to coordinate, substantively and procedurally, the revisions and implementation of State implementation plans applicable to the nonattainment area concerned; and

(B) use photochemical grid modeling or any other analytical method determined by the Administrator, in his discretion, to be at least as effective.


The Administrator may not approve any revision of a State implementation plan submitted under this part for a State in which part of a multi-State ozone nonattainment area is located if the plan revision for that State fails to comply with the requirements of this subsection.

(2) Failure to demonstrate attainment

If any State in which there is located a portion of a multi-State ozone nonattainment area fails to provide a demonstration of attainment of the national ambient air quality standard for ozone in that portion within the required period, the State may petition the Administrator to make a finding that the State would have been able to make such demonstration but for the failure of one or more other States in which other portions of the area are located to commit to the implementation of all measures required under this section (relating to plan submissions and requirements for ozone nonattainment areas). If the Administrator makes such finding, the provisions of section 7509 of this title (relating to sanctions) shall not apply, by reason of the failure to make such demonstration, in the portion of the multi-State ozone nonattainment area within the State submitting such petition.

(July 14, 1955, ch. 360, title I, §182, as added Pub. L. 101–549, title I, §103, Nov. 15, 1990, 104 Stat. 2426; amended Pub. L. 104–70, §1, Dec. 23, 1995, 109 Stat. 773.)


Editorial Notes

References in Text

The Natural Gas Policy Act of 1978, referred to in subsec. (e)(3), is Pub. L. 95–621, Nov. 9, 1978, 92 Stat. 3350. Title III of the Act is classified generally to subchapter III (§3361 et seq.) of chapter 60 of Title 15, Commerce and Trade. For complete classification of this Act to the Code, see Short Title note set out under section 3301 of Title 15 and Tables.

Amendments

1995—Subsec. (d)(1)(B). Pub. L. 104–70 amended subpar. (B) generally. Prior to amendment, subpar. (B) read as follows: "Within 2 years after November 15, 1990, the State shall submit a revision requiring employers in such area to implement programs to reduce work-related vehicle trips and miles traveled by employees. Such revision shall be developed in accordance with guidance issued by the Administrator pursuant to section 7408(f) of this title and shall, at a minimum, require that each employer of 100 or more persons in such area increase average passenger occupancy per vehicle in commuting trips between home and the workplace during peak travel periods by not less than 25 percent above the average vehicle occupancy for all such trips in the area at the time the revision is submitted. The guidance of the Administrator may specify average vehicle occupancy rates which vary for locations within a nonattainment area (suburban, center city, business district) or among nonattainment areas reflecting existing occupancy rates and the availability of high occupancy modes. The revision shall provide that each employer subject to a vehicle occupancy requirement shall submit a compliance plan within 2 years after the date the revision is submitted which shall convincingly demonstrate compliance with the requirements of this paragraph not later than 4 years after such date."


Statutory Notes and Related Subsidiaries

Moratorium on Certain Emissions Testing Requirements

Pub. L. 104–59, title III, §348, Nov. 28, 1995, 109 Stat. 617, provided that:

"(a) In General.—The Administrator of the Environmental Protection Agency (hereinafter in this section referred to as the 'Administrator') shall not require adoption or implementation by a State of a test-only I/M240 enhanced vehicle inspection and maintenance program as a means of compliance with section 182 or 187 of the Clean Air Act (42 U.S.C. 7511a; 7512a), but the Administrator may approve such a program if a State chooses to adopt the program as a means of compliance with such section.

"(b) Limitation on Plan Disapproval.—The Administrator shall not disapprove or apply an automatic discount to a State implementation plan revision under section 182 or 187 of the Clean Air Act (42 U.S.C. 7511a; 7512a) on the basis of a policy, regulation, or guidance providing for a discount of emissions credits because the inspection and maintenance program in such plan revision is decentralized or a test-and-repair program.

"(c) Emissions Reduction Credits.—

"(1) State plan revision; approval.—Within 120 days of the date of the enactment of this subsection [Nov. 28, 1995], a State may submit an implementation plan revision proposing an interim inspection and maintenance program under section 182 or 187 of the Clean Air Act (42 U.S.C. 7511a; 7512a). The Administrator shall approve the program based on the full amount of credits proposed by the State for each element of the program if the proposed credits reflect good faith estimates by the State and the revision is otherwise in compliance with such Act. If, within such 120-day period, the State submits to the Administrator proposed revisions to the implementation plan, has all of the statutory authority necessary to implement the revisions, and has proposed a regulation to make the revisions, the Administrator may approve the revisions without regard to whether or not such regulation has been issued as a final regulation by the State.

"(2) Expiration of interim approval.—The interim approval shall expire on the earlier of (A) the last day of the 18-month period beginning on the date of the interim approval, or (B) the date of final approval. The interim approval may not be extended.

"(3) Final approval.—The Administrator shall grant final approval of the revision based on the credits proposed by the State during or after the period of interim approval if data collected on the operation of the State program demonstrates that the credits are appropriate and the revision is otherwise in compliance with the Clean Air Act [42 U.S.C. 7401 et seq.].

"(4) Basis of approval; no automatic discount.—Any determination with respect to interim or full approval shall be based on the elements of the program and shall not apply any automatic discount because the program is decentralized or a test-and-repair program."

1 So in original. Probably should be "subparagraph".

2 So in original. Probably should be section "7625".

3 So in original. Probably should be "increased".

4 So in original. No subpar. (B) has been enacted.

5 So in original. Probably should be "subsections".

6 So in original. Probably should be "paragraphs".

7 So in original. Probably should be "de minimis".

8 So in original. Probably should be "include".

§7511b. Federal ozone measures

(a) Control techniques guidelines for VOC sources

Within 3 years after November 15, 1990, the Administrator shall issue control techniques guidelines, in accordance with section 7408 of this title, for 11 categories of stationary sources of VOC emissions for which such guidelines have not been issued as of November 15, 1990, not including the categories referred to in paragraphs (3) and (4) of subsection (b) of this section. The Administrator may issue such additional control techniques guidelines as the Administrator deems necessary.

(b) Existing and new CTGS

(1) Within 36 months after November 15, 1990, and periodically thereafter, the Administrator shall review and, if necessary, update control technique guidance issued under section 7408 of this title before November 15, 1990.

(2) In issuing the guidelines the Administrator shall give priority to those categories which the Administrator considers to make the most significant contribution to the formation of ozone air pollution in ozone nonattainment areas, including hazardous waste treatment, storage, and disposal facilities which are permitted under subtitle C of the Solid Waste Disposal Act [42 U.S.C. 6921 et seq.]. Thereafter the Administrator shall periodically review and, if necessary, revise such guidelines.

(3) Within 3 years after November 15, 1990, the Administrator shall issue control techniques guidelines in accordance with section 7408 of this title to reduce the aggregate emissions of volatile organic compounds into the ambient air from aerospace coatings and solvents. Such control techniques guidelines shall, at a minimum, be adequate to reduce aggregate emissions of volatile organic compounds into the ambient air from the application of such coatings and solvents to such level as the Administrator determines may be achieved through the adoption of best available control measures. Such control technology guidance shall provide for such reductions in such increments and on such schedules as the Administrator determines to be reasonable, but in no event later than 10 years after the final issuance of such control technology guidance. In developing control technology guidance under this subsection, the Administrator shall consult with the Secretary of Defense, the Secretary of Transportation, and the Administrator of the National Aeronautics and Space Administration with regard to the establishment of specifications for such coatings. In evaluating VOC reduction strategies, the guidance shall take into account the applicable requirements of section 7412 of this title and the need to protect stratospheric ozone.

(4) Within 3 years after November 15, 1990, the Administrator shall issue control techniques guidelines in accordance with section 7408 of this title to reduce the aggregate emissions of volatile organic compounds and PM–10 into the ambient air from paints, coatings, and solvents used in shipbuilding operations and ship repair. Such control techniques guidelines shall, at a minimum, be adequate to reduce aggregate emissions of volatile organic compounds and PM–10 into the ambient air from the removal or application of such paints, coatings, and solvents to such level as the Administrator determines may be achieved through the adoption of the best available control measures. Such control techniques guidelines shall provide for such reductions in such increments and on such schedules as the Administrator determines to be reasonable, but in no event later than 10 years after the final issuance of such control technology guidance. In developing control techniques guidelines under this subsection, the Administrator shall consult with the appropriate Federal agencies.

(c) Alternative control techniques

Within 3 years after November 15, 1990, the Administrator shall issue technical documents which identify alternative controls for all categories of stationary sources of volatile organic compounds and oxides of nitrogen which emit, or have the potential to emit 25 tons per year or more of such air pollutant. The Administrator shall revise and update such documents as the Administrator determines necessary.

(d) Guidance for evaluating cost-effectiveness

Within 1 year after November 15, 1990, the Administrator shall provide guidance to the States to be used in evaluating the relative cost-effectiveness of various options for the control of emissions from existing stationary sources of air pollutants which contribute to nonattainment of the national ambient air quality standards for ozone.

(e) Control of emissions from certain sources

(1) Definitions

For purposes of this subsection—

(A) Best available controls

The term "best available controls" means the degree of emissions reduction that the Administrator determines, on the basis of technological and economic feasibility, health, environmental, and energy impacts, is achievable through the application of the most effective equipment, measures, processes, methods, systems or techniques, including chemical reformulation, product or feedstock substitution, repackaging, and directions for use, consumption, storage, or disposal.

(B) Consumer or commercial product

The term "consumer or commercial product" means any substance, product (including paints, coatings, and solvents), or article (including any container or packaging) held by any person, the use, consumption, storage, disposal, destruction, or decomposition of which may result in the release of volatile organic compounds. The term does not include fuels or fuel additives regulated under section 7545 of this title, or motor vehicles, non-road vehicles, and non-road engines as defined under section 7550 of this title.

(C) Regulated entities

The term "regulated entities" means—

(i) manufacturers, processors, wholesale distributors, or importers of consumer or commercial products for sale or distribution in interstate commerce in the United States; or

(ii) manufacturers, processors, wholesale distributors, or importers that supply the entities listed under clause (i) with such products for sale or distribution in interstate commerce in the United States.

(2) Study and report

(A) Study

The Administrator shall conduct a study of the emissions of volatile organic compounds into the ambient air from consumer and commercial products (or any combination thereof) in order to—

(i) determine their potential to contribute to ozone levels which violate the national ambient air quality standard for ozone; and

(ii) establish criteria for regulating consumer and commercial products or classes or categories thereof which shall be subject to control under this subsection.


The study shall be completed and a report submitted to Congress not later than 3 years after November 15, 1990.

(B) Consideration of certain factors

In establishing the criteria under subparagraph (A)(ii), the Administrator shall take into consideration each of the following:

(i) The uses, benefits, and commercial demand of consumer and commercial products.

(ii) The health or safety functions (if any) served by such consumer and commercial products.

(iii) Those consumer and commercial products which emit highly reactive volatile organic compounds into the ambient air.

(iv) Those consumer and commercial products which are subject to the most cost-effective controls.

(v) The availability of alternatives (if any) to such consumer and commercial products which are of comparable costs, considering health, safety, and environmental impacts.

(3) Regulations to require emission reductions

(A) In general

Upon submission of the final report under paragraph (2), the Administrator shall list those categories of consumer or commercial products that the Administrator determines, based on the study, account for at least 80 percent of the VOC emissions, on a reactivity-adjusted basis, from consumer or commercial products in areas that violate the NAAQS for ozone. Credit toward the 80 percent emissions calculation shall be given for emission reductions from consumer or commercial products made after November 15, 1990. At such time, the Administrator shall divide the list into 4 groups establishing priorities for regulation based on the criteria established in paragraph (2). Every 2 years after promulgating such list, the Administrator shall regulate one group of categories until all 4 groups are regulated. The regulations shall require best available controls as defined in this section. Such regulations may exempt health use products for which the Administrator determines there is no suitable substitute. In order to carry out this section, the Administrator may, by regulation, control or prohibit any activity, including the manufacture or introduction into commerce, offering for sale, or sale of any consumer or commercial product which results in emission of volatile organic compounds into the ambient air.

(B) Regulated entities

Regulations under this subsection may be imposed only with respect to regulated entities.

(C) Use of CTGS

For any consumer or commercial product the Administrator may issue control techniques guidelines under this chapter in lieu of regulations required under subparagraph (A) if the Administrator determines that such guidance will be substantially as effective as regulations in reducing emissions of volatile organic compounds which contribute to ozone levels in areas which violate the national ambient air quality standard for ozone.

(4) Systems of regulation

The regulations under this subsection may include any system or systems of regulation as the Administrator may deem appropriate, including requirements for registration and labeling, self-monitoring and reporting, prohibitions, limitations, or economic incentives (including marketable permits and auctions of emissions rights) concerning the manufacture, processing, distribution, use, consumption, or disposal of the product.

(5) Special fund

Any amounts collected by the Administrator under such regulations shall be deposited in a special fund in the United States Treasury for licensing and other services, which thereafter shall be available until expended, subject to annual appropriation Acts, solely to carry out the activities of the Administrator for which such fees, charges, or collections are established or made.

(6) Enforcement

Any regulation established under this subsection shall be treated, for purposes of enforcement of this chapter, as a standard under section 7411 of this title and any violation of such regulation shall be treated as a violation of a requirement of section 7411(e) of this title.

(7) State administration

Each State may develop and submit to the Administrator a procedure under State law for implementing and enforcing regulations promulgated under this subsection. If the Administrator finds the State procedure is adequate, the Administrator shall approve such procedure. Nothing in this paragraph shall prohibit the Administrator from enforcing any applicable regulations under this subsection.

(8) Size, etc.

No regulations regarding the size, shape, or labeling of a product may be promulgated, unless the Administrator determines such regulations to be useful in meeting any national ambient air quality standard.

(9) State consultation

Any State which proposes regulations other than those adopted under this subsection shall consult with the Administrator regarding whether any other State or local subdivision has promulgated or is promulgating regulations on any products covered under this part. The Administrator shall establish a clearinghouse of information, studies, and regulations proposed and promulgated regarding products covered under this subsection and disseminate such information collected as requested by State or local subdivisions.

(f) Tank vessel standards

(1) Schedule for standards

(A) Within 2 years after November 15, 1990, the Administrator, in consultation with the Secretary of the Department in which the Coast Guard is operating, shall promulgate standards applicable to the emission of VOCs and any other air pollutant from loading and unloading of tank vessels (as that term is defined in section 2101 of title 46) which the Administrator finds causes, or contributes to, air pollution that may be reasonably anticipated to endanger public health or welfare. Such standards shall require the application of reasonably available control technology, considering costs, any nonair-quality benefits, environmental impacts, energy requirements and safety factors associated with alternative control techniques. To the extent practicable such standards shall apply to loading and unloading facilities and not to tank vessels.

(B) Any regulation prescribed under this subsection (and any revision thereof) shall take effect after such period as the Administrator finds (after consultation with the Secretary of the department 1 in which the Coast Guard is operating) necessary to permit the development and application of the requisite technology, giving appropriate consideration to the cost of compliance within such period, except that the effective date shall not be more than 2 years after promulgation of such regulations.

(2) Regulations on equipment safety

Within 6 months after November 15, 1990, the Secretary of the Department in which the Coast Guard is operating shall issue regulations to ensure the safety of the equipment and operations which are to control emissions from the loading and unloading of tank vessels, under section 3703 of title 46 and section 1225 2 of title 33. The standards promulgated by the Administrator under paragraph (1) and the regulations issued by a State or political subdivision regarding emissions from the loading and unloading of tank vessels shall be consistent with the regulations regarding safety of the Department in which the Coast Guard is operating.

(3) Agency authority

(A) The Administrator shall ensure compliance with the tank vessel emission standards prescribed under paragraph (1)(A). The Secretary of the Department in which the Coast Guard is operating shall also ensure compliance with the tank vessel standards prescribed under paragraph (1)(A).

(B) The Secretary of the Department in which the Coast Guard is operating shall ensure compliance with the regulations issued under paragraph (2).

(4) State or local standards

After the Administrator promulgates standards under this section, no State or political subdivision thereof may adopt or attempt to enforce any standard respecting emissions from tank vessels subject to regulation under paragraph (1) unless such standard is no less stringent than the standards promulgated under paragraph (1).

(5) Enforcement

Any standard established under paragraph (1)(A) shall be treated, for purposes of enforcement of this chapter, as a standard under section 7411 of this title and any violation of such standard shall be treated as a violation of a requirement of section 7411(e) of this title.

(g) Ozone design value study

The Administrator shall conduct a study of whether the methodology in use by the Environmental Protection Agency as of November 15, 1990, for establishing a design value for ozone provides a reasonable indicator of the ozone air quality of ozone nonattainment areas. The Administrator shall obtain input from States, local subdivisions thereof, and others. The study shall be completed and a report submitted to Congress not later than 3 years after November 15, 1990. The results of the study shall be subject to peer and public review before submitting it to Congress.

(h) Vehicles entering ozone nonattainment areas

(1) Authority regarding ozone inspection and maintenance testing

(A) In general

No noncommercial motor vehicle registered in a foreign country and operated by a United States citizen or by an alien who is a permanent resident of the United States, or who holds a visa for the purposes of employment or educational study in the United States, may enter a covered ozone nonattainment area from a foreign country bordering the United States and contiguous to the nonattainment area more than twice in a single calendar-month period, if State law has requirements for the inspection and maintenance of such vehicles under the applicable implementation plan in the nonattainment area.

(B) Applicability

Subparagraph (A) shall not apply if the operator presents documentation at the United States border entry point establishing that the vehicle has complied with such inspection and maintenance requirements as are in effect and are applicable to motor vehicles of the same type and model year.

(2) Sanctions for violations

The President may impose and collect from the operator of any motor vehicle who violates, or attempts to violate, paragraph (1) a civil penalty of not more than $200 for the second violation or attempted violation and $400 for the third and each subsequent violation or attempted violation.

(3) State election

The prohibition set forth in paragraph (1) shall not apply in any State that elects to be exempt from the prohibition. Such an election shall take effect upon the President's receipt of written notice from the Governor of the State notifying the President of such election.

(4) Alternative approach

The prohibition set forth in paragraph (1) shall not apply in a State, and the President may implement an alternative approach, if—

(A) the Governor of the State submits to the President a written description of an alternative approach to facilitate the compliance, by some or all foreign-registered motor vehicles, with the motor vehicle inspection and maintenance requirements that are—

(i) related to emissions of air pollutants;

(ii) in effect under the applicable implementation plan in the covered ozone nonattainment area; and

(iii) applicable to motor vehicles of the same types and model years as the foreign-registered motor vehicles; and


(B) the President approves the alternative approach as facilitating compliance with the motor vehicle inspection and maintenance requirements referred to in subparagraph (A).

(5) Definition of covered ozone nonattainment area

In this section, the term "covered ozone nonattainment area" means a Serious Area, as classified under section 7511 of this title as of October 27, 1998.

(July 14, 1955, ch. 360, title I, §183, as added Pub. L. 101–549, title I, §103, Nov. 15, 1990, 104 Stat. 2443; amended Pub. L. 105–286, §2, Oct. 27, 1998, 112 Stat. 2773.)


Editorial Notes

References in Text

The Solid Waste Disposal Act, referred to in subsec. (b)(2), is title II of Pub. L. 89–272, Oct. 20, 1965, 79 Stat. 997, as amended generally by Pub. L. 94–580, §2, Oct. 21, 1976, 90 Stat. 2795. Subtitle C of the Act is classified generally to subchapter III (§6921 et seq.) of chapter 82 of this title. For complete classification of this Act to the Code, see Short Title note set out under section 6901 of this title and Tables.

Section 1225 of title 33, referred to in subsec. (f)(2), was repealed by Pub. L. 115–282, title IV, §402(e), Dec. 4, 2018, 132 Stat. 4264. See Transitional and Savings Provisions note preceding section 101 of Title 46, Shipping, and section 70011 of Title 46.

Amendments

1998—Subsec. (h). Pub. L. 105–286 added subsec. (h).


Statutory Notes and Related Subsidiaries

Effective Date of 1998 Amendment; Publication of Prohibition

Pub. L. 105–286, §3, Oct. 27, 1998, 112 Stat. 2774, provided that:

"(a) In General.—The amendment made by section 2 [amending this section] takes effect 180 days after the date of the enactment of this Act [Oct. 27, 1998]. Nothing in that amendment shall require action that is inconsistent with the obligations of the United States under any international agreement.

"(b) Information.—As soon as practicable after the date of the enactment of this Act, the appropriate agency of the United States shall distribute information to publicize the prohibition set forth in the amendment made by section 2."

Transfer of Functions

For transfer of authorities, functions, personnel, and assets of the Coast Guard, including the authorities and functions of the Secretary of Transportation relating thereto, to the Department of Homeland Security, and for treatment of related references, see sections 468(b), 551(d), 552(d), and 557 of Title 6, Domestic Security, and the Department of Homeland Security Reorganization Plan of November 25, 2002, as modified, set out as a note under section 542 of Title 6.

1 So in original. Probably should be capitalized.

2 See References in Text note below.

§7511c. Control of interstate ozone air pollution

(a) Ozone transport regions

A single transport region for ozone (within the meaning of section 7506a(a) of this title), comprised of the States of Connecticut, Delaware, Maine, Maryland, Massachusetts, New Hampshire, New Jersey, New York, Pennsylvania, Rhode Island, Vermont, and the Consolidated Metropolitan Statistical Area that includes the District of Columbia, is hereby established by operation of law. The provisions of section 7506a(a)(1) and (2) of this title shall apply with respect to the transport region established under this section and any other transport region established for ozone, except to the extent inconsistent with the provisions of this section. The Administrator shall convene the commission required (under section 7506a(b) of this title) as a result of the establishment of such region within 6 months of November 15, 1990.

(b) Plan provisions for States in ozone transport regions

(1) In accordance with section 7410 of this title, not later than 2 years after November 15, 1990 (or 9 months after the subsequent inclusion of a State in a transport region established for ozone), each State included within a transport region established for ozone shall submit a State implementation plan or revision thereof to the Administrator which requires the following—

(A) that each area in such State that is in an ozone transport region, and that is a metropolitan statistical area or part thereof with a population of 100,000 or more comply with the provisions of section 7511a(c)(2)(A) of this title (pertaining to enhanced vehicle inspection and maintenance programs); and

(B) implementation of reasonably available control technology with respect to all sources of volatile organic compounds in the State covered by a control techniques guideline issued before or after November 15, 1990.


(2) Within 3 years after November 15, 1990, the Administrator shall complete a study identifying control measures capable of achieving emission reductions comparable to those achievable through vehicle refueling controls contained in section 7511a(b)(3) of this title, and such measures or such vehicle refueling controls shall be implemented in accordance with the provisions of this section. Notwithstanding other deadlines in this section, the applicable implementation plan shall be revised to reflect such measures within 1 year of completion of the study. For purposes of this section any stationary source that emits or has the potential to emit at least 50 tons per year of volatile organic compounds shall be considered a major stationary source and subject to the requirements which would be applicable to major stationary sources if the area were classified as a Moderate nonattainment area.

(c) Additional control measures

(1) Recommendations

Upon petition of any State within a transport region established for ozone, and based on a majority vote of the Governors on the Commission 1 (or their designees), the Commission 1 may, after notice and opportunity for public comment, develop recommendations for additional control measures to be applied within all or a part of such transport region if the commission determines such measures are necessary to bring any area in such region into attainment by the dates provided by this subpart. The commission shall transmit such recommendations to the Administrator.

(2) Notice and review

Whenever the Administrator receives recommendations prepared by a commission pursuant to paragraph (1) (the date of receipt of which shall hereinafter in this section be referred to as the "receipt date"), the Administrator shall—

(A) immediately publish in the Federal Register a notice stating that the recommendations are available and provide an opportunity for public hearing within 90 days beginning on the receipt date; and

(B) commence a review of the recommendations to determine whether the control measures in the recommendations are necessary to bring any area in such region into attainment by the dates provided by this subpart and are otherwise consistent with this chapter.

(3) Consultation

In undertaking the review required under paragraph (2)(B), the Administrator shall consult with members of the commission of the affected States and shall take into account the data, views, and comments received pursuant to paragraph (2)(A).

(4) Approval and disapproval

Within 9 months after the receipt date, the Administrator shall (A) determine whether to approve, disapprove, or partially disapprove and partially approve the recommendations; (B) notify the commission in writing of such approval, disapproval, or partial disapproval; and (C) publish such determination in the Federal Register. If the Administrator disapproves or partially disapproves the recommendations, the Administrator shall specify—

(i) why any disapproved additional control measures are not necessary to bring any area in such region into attainment by the dates provided by this subpart or are otherwise not consistent with the 2 chapter; and

(ii) recommendations concerning equal or more effective actions that could be taken by the commission to conform the disapproved portion of the recommendations to the requirements of this section.

(5) Finding

Upon approval or partial approval of recommendations submitted by a commission, the Administrator shall issue to each State which is included in the transport region and to which a requirement of the approved plan applies, a finding under section 7410(k)(5) of this title that the implementation plan for such State is inadequate to meet the requirements of section 7410(a)(2)(D) of this title. Such finding shall require each such State to revise its implementation plan to include the approved additional control measures within one year after the finding is issued.

(d) Best available air quality monitoring and modeling

For purposes of this section, not later than 6 months after November 15, 1990, the Administrator shall promulgate criteria for purposes of determining the contribution of sources in one area to concentrations of ozone in another area which is a nonattainment area for ozone. Such criteria shall require that the best available air quality monitoring and modeling techniques be used for purposes of making such determinations.

(July 14, 1955, ch. 360, title I, §184, as added Pub. L. 101–549, title I, §103, Nov. 15, 1990, 104 Stat. 2448.)

1 So in original. Probably should not be capitalized.

2 So in original. Probably should be "this".

§7511d. Enforcement for Severe and Extreme ozone nonattainment areas for failure to attain

(a) General rule

Each implementation plan revision required under section 7511a(d) and (e) of this title (relating to the attainment plan for Severe and Extreme ozone nonattainment areas) shall provide that, if the area to which such plan revision applies has failed to attain the national primary ambient air quality standard for ozone by the applicable attainment date, each major stationary source of VOCs located in the area shall, except as otherwise provided under subsection (c), pay a fee to the State as a penalty for such failure, computed in accordance with subsection (b), for each calendar year beginning after the attainment date, until the area is redesignated as an attainment area for ozone. Each such plan revision should include procedures for assessment and collection of such fees.

(b) Computation of fee

(1) Fee amount

The fee shall equal $5,000, adjusted in accordance with paragraph (3), per ton of VOC emitted by the source during the calendar year in excess of 80 percent of the baseline amount, computed under paragraph (2).

(2) Baseline amount

For purposes of this section, the baseline amount shall be computed, in accordance with such guidance as the Administrator may provide, as the lower of the amount of actual VOC emissions ("actuals") or VOC emissions allowed under the permit applicable to the source (or, if no such permit has been issued for the attainment year, the amount of VOC emissions allowed under the applicable implementation plan ("allowables")) during the attainment year. Notwithstanding the preceding sentence, the Administrator may issue guidance authorizing the baseline amount to be determined in accordance with the lower of average actuals or average allowables, determined over a period of more than one calendar year. Such guidance may provide that such average calculation for a specific source may be used if that source's emissions are irregular, cyclical, or otherwise vary significantly from year to year.

(3) Annual adjustment

The fee amount under paragraph (1) shall be adjusted annually, beginning in the year beginning after 1990, in accordance with section 7661a(b)(3)(B)(v) of this title (relating to inflation adjustment).

(c) Exception

Notwithstanding any provision of this section, no source shall be required to pay any fee under subsection (a) with respect to emissions during any year that is treated as an Extension Year under section 7511(a)(5) of this title.

(d) Fee collection by Administrator

If the Administrator has found that the fee provisions of the implementation plan do not meet the requirements of this section, or if the Administrator makes a finding that the State is not administering and enforcing the fee required under this section, the Administrator shall, in addition to any other action authorized under this subchapter, collect, in accordance with procedures promulgated by the Administrator, the unpaid fees required under subsection (a). If the Administrator makes such a finding under section 7509(a)(4) of this title, the Administrator may collect fees for periods before the determination, plus interest computed in accordance with section 6621(a)(2) of title 26 (relating to computation of interest on underpayment of Federal taxes), to the extent the Administrator finds such fees have not been paid to the State. The provisions of clauses (ii) through (iii) of section 7661a(b)(3)(C) of this title (relating to penalties and use of the funds, respectively) shall apply with respect to fees collected under this subsection.

(e) Exemptions for certain small areas

For areas with a total population under 200,000 which fail to attain the standard by the applicable attainment date, no sanction under this section or under any other provision of this chapter shall apply if the area can demonstrate, consistent with guidance issued by the Administrator, that attainment in the area is prevented because of ozone or ozone precursors transported from other areas. The prohibition applies only in cases in which the area has met all requirements and implemented all measures applicable to the area under this chapter.

(July 14, 1955, ch. 360, title I, §185, as added Pub. L. 101–549, title I, §103, Nov. 15, 1990, 104 Stat. 2450.)

§7511e. Transitional areas

If an area designated as an ozone nonattainment area as of November 15, 1990, has not violated the national primary ambient air quality standard for ozone for the 36-month period commencing on January 1, 1987, and ending on December 31, 1989, the Administrator shall suspend the application of the requirements of this subpart to such area until December 31, 1991. By June 30, 1992, the Administrator shall determine by order, based on the area's design value as of the attainment date, whether the area attained such standard by December 31, 1991. If the Administrator determines that the area attained the standard, the Administrator shall require, as part of the order, the State to submit a maintenance plan for the area within 12 months of such determination. If the Administrator determines that the area failed to attain the standard, the Administrator shall, by June 30, 1992, designate the area as nonattainment under section 7407(d)(4) of this title.

(July 14, 1955, ch. 360, title I, §185A, as added Pub. L. 101–549, title I, §103, Nov. 15, 1990, 104 Stat. 2451.)

§7511f. NOx and VOC study

The Administrator, in conjunction with the National Academy of Sciences, shall conduct a study on the role of ozone precursors in tropospheric ozone formation and control. The study shall examine the roles of NOx and VOC emission reductions, the extent to which NOx reductions may contribute (or be counterproductive) to achievement of attainment in different nonattainment areas, the sensitivity of ozone to the control of NOx, the availability and extent of controls for NOx, the role of biogenic VOC emissions, and the basic information required for air quality models. The study shall be completed and a proposed report made public for 30 days comment within 1 year of November 15, 1990, and a final report shall be submitted to Congress within 15 months after November 15, 1990. The Administrator shall utilize all available information and studies, as well as develop additional information, in conducting the study required by this section.

(July 14, 1955, ch. 360, title I, §185B, as added Pub. L. 101–549, title I, §103, Nov. 15, 1990, 104 Stat. 2452.)

subpart 3—additional provisions for carbon monoxide nonattainment areas

§7512. Classification and attainment dates

(a) Classification by operation of law and attainment dates for nonattainment areas

(1) Each area designated nonattainment for carbon monoxide pursuant to section 7407(d) of this title shall be classified at the time of such designation under table 1, by operation of law, as a Moderate Area or a Serious Area based on the design value for the area. The design value shall be calculated according to the interpretation methodology issued by the Administrator most recently before November 15, 1990. For each area classified under this subsection, the primary standard attainment date for carbon monoxide shall be as expeditiously as practicable but not later than the date provided in table 1:

TABLE 3 1
Area

classification

Design valuePrimary standard attainment date
Moderate 9.1–16.4 ppm December 31, 1995
Serious 16.5 and above December 31, 2000

(2) At the time of publication of the notice required under section 7407 of this title (designating carbon monoxide nonattainment areas), the Administrator shall publish a notice announcing the classification of each such carbon monoxide nonattainment area. The provisions of section 7502(a)(1)(B) of this title (relating to lack of notice-and-comment and judicial review) shall apply with respect to such classification.

(3) If an area classified under paragraph (1), table 1, would have been classified in another category if the design value in the area were 5 percent greater or 5 percent less than the level on which such classification was based, the Administrator may, in the Administrator's discretion, within 90 days after November 15, 1990, by the procedure required under paragraph (2), adjust the classification of the area. In making such adjustment, the Administrator may consider the number of exceedances of the national primary ambient air quality standard for carbon monoxide in the area, the level of pollution transport between the area and the other affected areas, and the mix of sources and air pollutants in the area. The Administrator may make the same adjustment for purposes of paragraphs (2), (3), (6), and (7) of section 7512a(a) of this title.

(4) Upon application by any State, the Administrator may extend for 1 additional year (hereinafter in this subpart referred to as the "Extension Year") the date specified in table 1 of subsection (a) if—

(A) the State has complied with all requirements and commitments pertaining to the area in the applicable implementation plan, and

(B) no more than one exceedance of the national ambient air quality standard level for carbon monoxide has occurred in the area in the year preceding the Extension Year.


No more than 2 one-year extensions may be issued under this paragraph for a single nonattainment area.

(b) New designations and reclassifications

(1) New designations to nonattainment

Any area that is designated attainment or unclassifiable for carbon monoxide under section 7407(d)(4) of this title, and that is subsequently redesignated to nonattainment for carbon monoxide under section 7407(d)(3) of this title, shall, at the time of the redesignation, be classified by operation of law in accordance with table 1 under subsections (a)(1) and (a)(4). Upon its classification, the area shall be subject to the same requirements under section 7410 of this title, subpart 1 of this part, and this subpart that would have applied had the area been so classified at the time of the notice under subsection (a)(2), except that any absolute, fixed date applicable in connection with any such requirement is extended by operation of law by a period equal to the length of time between November 15, 1990, and the date the area is classified.

(2) Reclassification of Moderate Areas upon failure to attain

(A) General rule

Within 6 months following the applicable attainment date for a carbon monoxide nonattainment area, the Administrator shall determine, based on the area's design value as of the attainment date, whether the area has attained the standard by that date. Any Moderate Area that the Administrator finds has not attained the standard by that date shall be reclassified by operation of law in accordance with table 1 of subsection (a)(1) as a Serious Area.

(B) Publication of notice

The Administrator shall publish a notice in the Federal Register, no later than 6 months following the attainment date, identifying each area that the Administrator has determined, under subparagraph (A), as having failed to attain and identifying the reclassification, if any, described under subparagraph (A).

(c) References to terms

Any reference in this subpart to a "Moderate Area" or a "Serious Area" shall be considered a reference to a Moderate Area or a Serious Area, respectively, as classified under this section.

(July 14, 1955, ch. 360, title I, §186, as added Pub. L. 101–549, title I, §104, Nov. 15, 1990, 104 Stat. 2452.)

1 So in original. Probably should be "TABLE 1".

§7512a. Plan submissions and requirements

(a) Moderate Areas

Each State in which all or part of a Moderate Area is located shall, with respect to the Moderate Area (or portion thereof, to the extent specified in guidance of the Administrator issued before November 15, 1990), submit to the Administrator the State implementation plan revisions (including the plan items) described under this subsection, within such periods as are prescribed under this subsection, except to the extent the State has made such submissions as of November 15, 1990:

(1) Inventory

No later than 2 years from November 15, 1990, the State shall submit a comprehensive, accurate, current inventory of actual emissions from all sources, as described in section 7502(c)(3) of this title, in accordance with guidance provided by the Administrator.

(2)(A) Vehicle miles traveled

No later than 2 years after November 15, 1990, for areas with a design value above 12.7 ppm at the time of classification, the plan revision shall contain a forecast of vehicle miles traveled in the nonattainment area concerned for each year before the year in which the plan projects the national ambient air quality standard for carbon monoxide to be attained in the area. The forecast shall be based on guidance which shall be published by the Administrator, in consultation with the Secretary of Transportation, within 6 months after November 15, 1990. The plan revision shall provide for annual updates of the forecasts to be submitted to the Administrator together with annual reports regarding the extent to which such forecasts proved to be accurate. Such annual reports shall contain estimates of actual vehicle miles traveled in each year for which a forecast was required.

(B) Special rule for Denver

Within 2 years after November 15, 1990, in the case of Denver, the State shall submit a revision that includes the transportation control measures as required in section 7511a(d)(1)(A) of this title except that such revision shall be for the purpose of reducing CO emissions rather than volatile organic compound emissions. If the State fails to include any such measure, the implementation plan shall contain an explanation of why such measure was not adopted and what emissions reduction measure was adopted to provide a comparable reduction in emissions, or reasons why such reduction is not necessary to attain the national primary ambient air quality standard for carbon monoxide.

(3) Contingency provisions

No later than 2 years after November 15, 1990, for areas with a design value above 12.7 ppm at the time of classification, the plan revision shall provide for the implementation of specific measures to be undertaken if any estimate of vehicle miles traveled in the area which is submitted in an annual report under paragraph (2) exceeds the number predicted in the most recent prior forecast or if the area fails to attain the national primary ambient air quality standard for carbon monoxide by the primary standard attainment date. Such measures shall be included in the plan revision as contingency measures to take effect without further action by the State or the Administrator if the prior forecast has been exceeded by an updated forecast or if the national standard is not attained by such deadline.

(4) Savings clause for vehicle inspection and maintenance provisions of the State implementation plan

Immediately after November 15, 1990, for any Moderate Area (or, within the Administrator's discretion, portion thereof), the plan for which is of the type described in section 7511a(a)(2)(B) of this title any provisions necessary to ensure that the applicable implementation plan includes the vehicle inspection and maintenance program described in section 7511a(a)(2)(B) of this title.

(5) Periodic inventory

No later than September 30, 1995, and no later than the end of each 3 year period thereafter, until the area is redesignated to attainment, a revised inventory meeting the requirements of subsection (a)(1).

(6) Enhanced vehicle inspection and maintenance

No later than 2 years after November 15, 1990, in the case of Moderate Areas with a design value greater than 12.7 ppm at the time of classification, a revision that includes provisions for an enhanced vehicle inspection and maintenance program as required in section 7511a(c)(3) of this title (concerning serious ozone nonattainment areas), except that such program shall be for the purpose of reducing carbon monoxide rather than hydrocarbon emissions.

(7) Attainment demonstration and specific annual emission reductions

In the case of Moderate Areas with a design value greater than 12.7 ppm at the time of classification, no later than 2 years after November 15, 1990, a revision to provide, and a demonstration that the plan as revised will provide, for attainment of the carbon monoxide NAAQS by the applicable attainment date and provisions for such specific annual emission reductions as are necessary to attain the standard by that date.


The Administrator may, in the Administrator's discretion, require States to submit a schedule for submitting any of the revisions or other items required under this subsection. In the case of Moderate Areas with a design value of 12.7 ppm or lower at the time of classification, the requirements of this subsection shall apply in lieu of any requirement that the State submit a demonstration that the applicable implementation plan provides for attainment of the carbon monoxide standard by the applicable attainment date.

(b) Serious Areas

(1) In general

Each State in which all or part of a Serious Area is located shall, with respect to the Serious Area, make the submissions (other than those required under subsection (a)(1)(B) 1) applicable under subsection (a) to Moderate Areas with a design value of 12.7 ppm or greater at the time of classification, and shall also submit the revision and other items described under this subsection.

(2) Vehicle miles traveled

Within 2 years after November 15, 1990, the State shall submit a revision that includes the transportation control measures as required in section 7511a(d)(1) of this title except that such revision shall be for the purpose of reducing CO emissions rather than volatile organic compound emissions. In the case of any such area (other than an area in New York State) which is a covered area (as defined in section 7586(a)(2)(B) of this title) for purposes of the Clean Fuel Fleet program under part C of subchapter II, if the State fails to include any such measure, the implementation plan shall contain an explanation of why such measure was not adopted and what emissions reduction measure was adopted to provide a comparable reduction in emissions, or reasons why such reduction is not necessary to attain the national primary ambient air quality standard for carbon monoxide.

(3) Oxygenated gasoline

(A) Within 2 years after November 15, 1990, the State shall submit a revision to require that gasoline sold, supplied, offered for sale or supply, dispensed, transported or introduced into commerce in the larger of—

(i) the Consolidated Metropolitan Statistical Area (as defined by the United States Office of Management and Budget) (CMSA) in which the area is located, or

(ii) if the area is not located in a CMSA, the Metropolitan Statistical Area (as defined by the United States Office of Management and Budget) in which the area is located,


be blended, during the portion of the year in which the area is prone to high ambient concentrations of carbon monoxide (as determined by the Administrator), with fuels containing such level of oxygen as is necessary, in combination with other measures, to provide for attainment of the carbon monoxide national ambient air quality standard by the applicable attainment date and maintenance of the national ambient air quality standard thereafter in the area. The revision shall provide that such requirement shall take effect no later than October 1, 1993, and shall include a program for implementation and enforcement of the requirement consistent with guidance to be issued by the Administrator.

(B) Notwithstanding subparagraph (A), the revision described in this paragraph shall not be required for an area if the State demonstrates to the satisfaction of the Administrator that the revision is not necessary to provide for attainment of the carbon monoxide national ambient air quality standard by the applicable attainment date and maintenance of the national ambient air quality standard thereafter in the area.

(c) Areas with significant stationary source emissions of CO

(1) Serious Areas

In the case of Serious Areas in which stationary sources contribute significantly to carbon monoxide levels (as determined under rules issued by the Administrator), the State shall submit a plan revision within 2 years after November 15, 1990, which provides that the term "major stationary source" includes (in addition to the sources described in section 7602 of this title) any stationary source which emits, or has the potential to emit, 50 tons per year or more of carbon monoxide.

(2) Waivers for certain areas

The Administrator may, on a case-by-case basis, waive any requirements that pertain to transportation controls, inspection and maintenance, or oxygenated fuels where the Administrator determines by rule that mobile sources of carbon monoxide do not contribute significantly to carbon monoxide levels in the area.

(3) Guidelines

Within 6 months after November 15, 1990, the Administrator shall issue guidelines for and rules determining whether stationary sources contribute significantly to carbon monoxide levels in an area.

(d) CO milestone

(1) Milestone demonstration

By March 31, 1996, each State in which all or part of a Serious Area is located shall submit to the Administrator a demonstration that the area has achieved a reduction in emissions of CO equivalent to the total of the specific annual emission reductions required by December 31, 1995. Such reductions shall be referred to in this subsection as the milestone.

(2) Adequacy of demonstration

A demonstration under this paragraph shall be submitted in such form and manner, and shall contain such information and analysis, as the Administrator shall require. The Administrator shall determine whether or not a State's demonstration is adequate within 90 days after the Administrator's receipt of a demonstration which contains the information and analysis required by the Administrator.

(3) Failure to meet emission reduction milestone

If a State fails to submit a demonstration under paragraph (1) within the required period, or if the Administrator notifies the State that the State has not met the milestone, the State shall, within 9 months after such a failure or notification, submit a plan revision to implement an economic incentive and transportation control program as described in section 7511a(g)(4) of this title. Such revision shall be sufficient to achieve the specific annual reductions in carbon monoxide emissions set forth in the plan by the attainment date.

(e) Multi-State CO nonattainment areas

(1) Coordination among States

Each State in which there is located a portion of a single nonattainment area for carbon monoxide which covers more than one State ("multi-State nonattainment area") shall take all reasonable steps to coordinate, substantively and procedurally, the revisions and implementation of State implementation plans applicable to the nonattainment area concerned. The Administrator may not approve any revision of a State implementation plan submitted under this part for a State in which part of a multi-State nonattainment area is located if the plan revision for that State fails to comply with the requirements of this subsection.

(2) Failure to demonstrate attainment

If any State in which there is located a portion of a multi-State nonattainment area fails to provide a demonstration of attainment of the national ambient air quality standard for carbon monoxide in that portion within the period required under this part the State may petition the Administrator to make a finding that the State would have been able to make such demonstration but for the failure of one or more other States in which other portions of the area are located to commit to the implementation of all measures required under this section (relating to plan submissions for carbon monoxide nonattainment areas). If the Administrator makes such finding, in the portion of the nonattainment area within the State submitting such petition, no sanction shall be imposed under section 7509 of this title or under any other provision of this chapter, by reason of the failure to make such demonstration.

(f) Reclassified areas

Each State containing a carbon monoxide nonattainment area reclassified under section 7512(b)(2) of this title shall meet the requirements of subsection (b) of this section, as may be applicable to the area as reclassified, according to the schedules prescribed in connection with such requirements, except that the Administrator may adjust any applicable deadlines (other than the attainment date) where such deadlines are shown to be infeasible.

(g) Failure of Serious Area to attain standard

If the Administrator determines under section 7512(b)(2) of this title that the national primary ambient air quality standard for carbon monoxide has not been attained in a Serious Area by the applicable attainment date, the State shall submit a plan revision for the area within 9 months after the date of such determination. The plan revision shall provide that a program of incentives and requirements as described in section 7511a(g)(4) of this title shall be applicable in the area, and such program, in combination with other elements of the revised plan, shall be adequate to reduce the total tonnage of emissions of carbon monoxide in the area by at least 5 percent per year in each year after approval of the plan revision and before attainment of the national primary ambient air quality standard for carbon monoxide.

(July 14, 1955, ch. 360, title I, §187, as added Pub. L. 101–549, title I, §104, Nov. 15, 1990, 104 Stat. 2454.)


Statutory Notes and Related Subsidiaries

Moratorium on Certain Emissions Testing Requirements

For provisions prohibiting Administrator of Environmental Protection Agency from requiring adoption or implementation by State of test-only I/M240 enhanced vehicle inspection and maintenance program as means of compliance with this section, with further provisions relating to plan disapproval and emissions reduction credits, see section 348 of Pub. L. 104–59, set out as a note under section 7511a of this title.

1 So in original. Subsec. (a)(1) of this section does not contain a subpar. (B).

subpart 4—additional provisions for particulate matter nonattainment areas

§7513. Classifications and attainment dates

(a) Initial classifications

Every area designated nonattainment for PM–10 pursuant to section 7407(d) of this title shall be classified at the time of such designation, by operation of law, as a moderate PM–10 nonattainment area (also referred to in this subpart as a "Moderate Area") at the time of such designation. At the time of publication of the notice under section 7407(d)(4) of this title (relating to area designations) for each PM–10 nonattainment area, the Administrator shall publish a notice announcing the classification of such area. The provisions of section 7502(a)(1)(B) of this title (relating to lack of notice-and-comment and judicial review) shall apply with respect to such classification.

(b) Reclassification as Serious

(1) Reclassification before attainment date

The Administrator may reclassify as a Serious PM–10 nonattainment area (identified in this subpart also as a "Serious Area") any area that the Administrator determines cannot practicably attain the national ambient air quality standard for PM–10 by the attainment date (as prescribed in subsection (c)) for Moderate Areas. The Administrator shall reclassify appropriate areas as Serious by the following dates:

(A) For areas designated nonattainment for PM–10 under section 7407(d)(4) of this title, the Administrator shall propose to reclassify appropriate areas by June 30, 1991, and take final action by December 31, 1991.

(B) For areas subsequently designated nonattainment, the Administrator shall reclassify appropriate areas within 18 months after the required date for the State's submission of a SIP for the Moderate Area.

(2) Reclassification upon failure to attain

Within 6 months following the applicable attainment date for a PM–10 nonattainment area, the Administrator shall determine whether the area attained the standard by that date. If the Administrator finds that any Moderate Area is not in attainment after the applicable attainment date—

(A) the area shall be reclassified by operation of law as a Serious Area; and

(B) the Administrator shall publish a notice in the Federal Register no later than 6 months following the attainment date, identifying the area as having failed to attain and identifying the reclassification described under subparagraph (A).

(c) Attainment dates

Except as provided under subsection (d), the attainment dates for PM–10 nonattainment areas shall be as follows:

(1) Moderate Areas

For a Moderate Area, the attainment date shall be as expeditiously as practicable but no later than the end of the sixth calendar year after the area's designation as nonattainment, except that, for areas designated nonattainment for PM–10 under section 7407(d)(4) of this title, the attainment date shall not extend beyond December 31, 1994.

(2) Serious Areas

For a Serious Area, the attainment date shall be as expeditiously as practicable but no later than the end of the tenth calendar year beginning after the area's designation as nonattainment, except that, for areas designated nonattainment for PM–10 under section 7407(d)(4) of this title, the date shall not extend beyond December 31, 2001.

(d) Extension of attainment date for Moderate Areas

Upon application by any State, the Administrator may extend for 1 additional year (hereinafter referred to as the "Extension Year") the date specified in paragraph 1 (c)(1) if—

(1) the State has complied with all requirements and commitments pertaining to the area in the applicable implementation plan; and

(2) no more than one exceedance of the 24-hour national ambient air quality standard level for PM–10 has occurred in the area in the year preceding the Extension Year, and the annual mean concentration of PM–10 in the area for such year is less than or equal to the standard level.


No more than 2 one-year extensions may be issued under the subsection for a single nonattainment area.

(e) Extension of attainment date for Serious Areas

Upon application by any State, the Administrator may extend the attainment date for a Serious Area beyond the date specified under subsection (c), if attainment by the date established under subsection (c) would be impracticable, the State has complied with all requirements and commitments pertaining to that area in the implementation plan, and the State demonstrates to the satisfaction of the Administrator that the plan for that area includes the most stringent measures that are included in the implementation plan of any State or are achieved in practice in any State, and can feasibly be implemented in the area. At the time of such application, the State must submit a revision to the implementation plan that includes a demonstration of attainment by the most expeditious alternative date practicable. In determining whether to grant an extension, and the appropriate length of time for any such extension, the Administrator may consider the nature and extent of nonattainment, the types and numbers of sources or other emitting activities in the area (including the influence of uncontrollable natural sources and transboundary emissions from foreign countries), the population exposed to concentrations in excess of the standard, the presence and concentration of potentially toxic substances in the mix of particulate emissions in the area, and the technological and economic feasibility of various control measures. The Administrator may not approve an extension until the State submits an attainment demonstration for the area. The Administrator may grant at most one such extension for an area, of no more than 5 years.

(f) Waivers for certain areas

The Administrator may, on a case-by-case basis, waive any requirement applicable to any Serious Area under this subpart where the Administrator determines that anthropogenic sources of PM–10 do not contribute significantly to the violation of the PM–10 standard in the area. The Administrator may also waive a specific date for attainment of the standard where the Administrator determines that nonanthropogenic sources of PM–10 contribute significantly to the violation of the PM–10 standard in the area.

(July 14, 1955, ch. 360, title I, §188, as added Pub. L. 101–549, title I, §105(a), Nov. 15, 1990, 104 Stat. 2458.)

1 So in original. Probably should be "subsection".

§7513a. Plan provisions and schedules for plan submissions

(a) Moderate Areas

(1) Plan provisions

Each State in which all or part of a Moderate Area is located shall submit, according to the applicable schedule under paragraph (2), an implementation plan that includes each of the following:

(A) For the purpose of meeting the requirements of section 7502(c)(5) of this title, a permit program providing that permits meeting the requirements of section 7503 of this title are required for the construction and operation of new and modified major stationary sources of PM–10.

(B) Either (i) a demonstration (including air quality modeling) that the plan will provide for attainment by the applicable attainment date; or (ii) a demonstration that attainment by such date is impracticable.

(C) Provisions to assure that reasonably available control measures for the control of PM–10 shall be implemented no later than December 10, 1993, or 4 years after designation in the case of an area classified as moderate after November 15, 1990.

(2) Schedule for plan submissions

A State shall submit the plan required under subparagraph (1) no later than the following:

(A) Within 1 year of November 15, 1990, for areas designated nonattainment under section 7407(d)(4) of this title, except that the provision required under subparagraph (1)(A) shall be submitted no later than June 30, 1992.

(B) 18 months after the designation as nonattainment, for those areas designated nonattainment after the designations prescribed under section 7407(d)(4) of this title.

(b) Serious Areas

(1) Plan provisions

In addition to the provisions submitted to meet the requirements of paragraph 1 (a)(1) (relating to Moderate Areas), each State in which all or part of a Serious Area is located shall submit an implementation plan for such area that includes each of the following:

(A) A demonstration (including air quality modeling)—

(i) that the plan provides for attainment of the PM–10 national ambient air quality standard by the applicable attainment date, or

(ii) for any area for which the State is seeking, pursuant to section 7513(e) of this title, an extension of the attainment date beyond the date set forth in section 7513(c) of this title, that attainment by that date would be impracticable, and that the plan provides for attainment by the most expeditious alternative date practicable.


(B) Provisions to assure that the best available control measures for the control of PM–10 shall be implemented no later than 4 years after the date the area is classified (or reclassified) as a Serious Area.

(2) Schedule for plan submissions

A State shall submit the demonstration required for an area under paragraph (1)(A) no later than 4 years after reclassification of the area to Serious, except that for areas reclassified under section 7513(b)(2) of this title, the State shall submit the attainment demonstration within 18 months after reclassification to Serious. A State shall submit the provisions described under paragraph (1)(B) no later than 18 months after reclassification of the area as a Serious Area.

(3) Major sources

For any Serious Area, the terms "major source" and "major stationary source" include any stationary source or group of stationary sources located within a contiguous area and under common control that emits, or has the potential to emit, at least 70 tons per year of PM–10.

(c) Milestones

(1) Plan revisions demonstrating attainment submitted to the Administrator for approval under this subpart shall contain quantitative milestones which are to be achieved every 3 years until the area is redesignated attainment and which demonstrate reasonable further progress, as defined in section 7501(1) of this title, toward attainment by the applicable date.

(2) Not later than 90 days after the date on which a milestone applicable to the area occurs, each State in which all or part of such area is located shall submit to the Administrator a demonstration that all measures in the plan approved under this section have been implemented and that the milestone has been met. A demonstration under this subsection shall be submitted in such form and manner, and shall contain such information and analysis, as the Administrator shall require. The Administrator shall determine whether or not a State's demonstration under this subsection is adequate within 90 days after the Administrator's receipt of a demonstration which contains the information and analysis required by the Administrator.

(3) If a State fails to submit a demonstration under paragraph (2) with respect to a milestone within the required period or if the Administrator determines that the area has not met any applicable milestone, the Administrator shall require the State, within 9 months after such failure or determination to submit a plan revision that assures that the State will achieve the next milestone (or attain the national ambient air quality standard for PM–10, if there is no next milestone) by the applicable date.

(d) Failure to attain

In the case of a Serious PM–10 nonattainment area in which the PM–10 standard is not attained by the applicable attainment date, the State in which such area is located shall, after notice and opportunity for public comment, submit within 12 months after the applicable attainment date, plan revisions which provide for attainment of the PM–10 air quality standard and, from the date of such submission until attainment, for an annual reduction in PM–10 or PM–10 precursor emissions within the area of not less than 5 percent of the amount of such emissions as reported in the most recent inventory prepared for such area.

(e) PM–10 precursors

The control requirements applicable under plans in effect under this part for major stationary sources of PM–10 shall also apply to major stationary sources of PM–10 precursors, except where the Administrator determines that such sources do not contribute significantly to PM–10 levels which exceed the standard in the area. The Administrator shall issue guidelines regarding the application of the preceding sentence.

(July 14, 1955, ch. 360, title I, §189, as added Pub. L. 101–549, title I, §105(a), Nov. 15, 1990, 104 Stat. 2460.)

1 So in original. Probably should be "subsection".

§7513b. Issuance of RACM and BACM guidance

The Administrator shall issue, in the same manner and according to the same procedure as guidance is issued under section 7408(c) of this title, technical guidance on reasonably available control measures and best available control measures for urban fugitive dust, and emissions from residential wood combustion (including curtailments and exemptions from such curtailments) and prescribed silvicultural and agricultural burning, no later than 18 months following November 15, 1990. The Administrator shall also examine other categories of sources contributing to nonattainment of the PM–10 standard, and determine whether additional guidance on reasonably available control measures and best available control measures is needed, and issue any such guidance no later than 3 years after November 15, 1990. In issuing guidelines and making determinations under this section, the Administrator (in consultation with the State) shall take into account emission reductions achieved, or expected to be achieved, under subchapter IV–A and other provisions of this chapter.

(July 14, 1955, ch. 360, title I, §190, as added Pub. L. 101–549, title I, §105(a), Nov. 15, 1990, 104 Stat. 2462.)

subpart 5—additional provisions for areas designated nonattainment for sulfur oxides, nitrogen dioxide, or lead

§7514. Plan submission deadlines

(a) Submission

Any State containing an area designated or redesignated under section 7407(d) of this title as nonattainment with respect to the national primary ambient air quality standards for sulfur oxides, nitrogen dioxide, or lead subsequent to November 15, 1990, shall submit to the Administrator, within 18 months of the designation, an applicable implementation plan meeting the requirements of this part.

(b) States lacking fully approved State implementation plans

Any State containing an area designated nonattainment with respect to national primary ambient air quality standards for sulfur oxides or nitrogen dioxide under section 7407(d)(1)(C)(i) of this title, but lacking a fully approved implementation plan complying with the requirements of this chapter (including this part) as in effect immediately before November 15, 1990, shall submit to the Administrator, within 18 months of November 15, 1990, an implementation plan meeting the requirements of subpart 1 (except as otherwise prescribed by section 7514a of this title).

(July 14, 1955, ch. 360, title I, §191, as added Pub. L. 101–549, title I, §106, Nov. 15, 1990, 104 Stat. 2463.)

§7514a. Attainment dates

(a) Plans under section 7514(a)

Implementation plans required under section 7514(a) of this title shall provide for attainment of the relevant primary standard as expeditiously as practicable but no later than 5 years from the date of the nonattainment designation.

(b) Plans under section 7514(b)

Implementation plans required under section 7514(b) of this title shall provide for attainment of the relevant primary national ambient air quality standard within 5 years after November 15, 1990.

(c) Inadequate plans

Implementation plans for nonattainment areas for sulfur oxides or nitrogen dioxide with plans that were approved by the Administrator before November 15, 1990, but, subsequent to such approval, were found by the Administrator to be substantially inadequate, shall provide for attainment of the relevant primary standard within 5 years from the date of such finding.

(July 14, 1955, ch. 360, title I, §192, as added Pub. L. 101–549, title I, §106, Nov. 15, 1990, 104 Stat. 2463.)

subpart 6—savings provisions

§7515. General savings clause

Each regulation, standard, rule, notice, order and guidance promulgated or issued by the Administrator under this chapter, as in effect before November 15, 1990, shall remain in effect according to its terms, except to the extent otherwise provided under this chapter, inconsistent with any provision of this chapter, or revised by the Administrator. No control requirement in effect, or required to be adopted by an order, settlement agreement, or plan in effect before November 15, 1990, in any area which is a nonattainment area for any air pollutant may be modified after November 15, 1990, in any manner unless the modification insures equivalent or greater emission reductions of such air pollutant.

(July 14, 1955, ch. 360, title I, §193, as added Pub. L. 101–549, title I, §108(l), Nov. 15, 1990, 104 Stat. 2469.)