Part B—Information and Reporting
§8421. Information
(a) Authority of Secretary
For purposes of carrying out his responsibilities under this chapter, the Secretary may require, under the authority of this chapter or any other authority administered by him, any person owning, operating or controlling any electric powerplant, or any other person otherwise subject to this chapter to submit such information and reports of any kind or nature directly to the Secretary necessary to implement the provisions of this chapter, and insure compliance with the provisions of this chapter, and any rule or order thereunder. The provisions of
(b) Authority of President and Federal Energy Regulatory Commission
In the case of responsibilities expressly given by this chapter to the President or the Federal Energy Regulatory Commission, subsection (a) shall be applied as if the references to the Secretary were references to the President or the Federal Energy Regulatory Commission, as the case may be.
(c) Natural gas usage by electric utilities
(1) For purposes of
(A) within 6 months after August 13, 1981, the total quantities of natural gas used as a primary energy source by each electric utility during calendar year 1977, and
(B) on a semiannual basis, the total quantities of natural gas used as a primary energy source during the previous 6-month period by each electric utility.
(2) Repealed.
(
Editorial Notes
References in Text
This chapter, referred to in subsecs. (a) and (b), was in the original "this Act", meaning
Amendments
1995—Subsec. (c)(2).
1987—Subsec. (a).
1981—Subsec. (c).
Statutory Notes and Related Subsidiaries
Effective Date of 1981 Amendment
Amendment by
§8422. Compliance report
(a) Generally
Any person owning, operating, or proposing to operate one or more existing electric powerplants required to come into compliance with the prohibitions of this chapter shall on or before January 1, 1980, and annually thereafter, submit to the Secretary a report identifying all such existing electric powerplants owned or operated by such person. Such report shall—
(1) set forth the anticipated schedule for compliance with the applicable requirements and prohibitions by each such electric powerplant;
(2) indicate proposed or existing contracts or other commitments or good faith negotiations for such contracts or commitments for coal or another alternate fuel, equipment, or combinations thereof, which would enable such powerplant to comply with such prohibitions; and
(3) identify those electric powerplants, if any, for which application for temporary or permanent exemption from the prohibitions of this chapter may be filed.
(b) Report on implementation of section 8484 plan
Any electric utility required to submit a conservation plan under
(
Editorial Notes
References in Text
This chapter, referred to in subsec. (a), was in the original "this Act", meaning
Amendments
1981—
Statutory Notes and Related Subsidiaries
Effective Date of 1981 Amendment
Amendment by