Part B—Closure of Facilities
§2601. Repealed. Pub. L. 113–66, div. C, title XXXI, §3146(e)(10), Dec. 26, 2013, 127 Stat. 1077
Section,
§2602. Reports in connection with permanent closures of Department of Energy defense nuclear facilities
(a) Training and job placement services plan
Not later than 120 days before a Department of Energy defense nuclear facility permanently ceases all production and processing operations, the Secretary of Energy shall submit to the Committees on Armed Services of the Senate and the House of Representatives a report containing a discussion of the training and job placement services needed to enable the employees at such facility to obtain employment in the defense environmental cleanup activities at such facility. The discussion shall include the actions that should be taken by the contractor operating and managing such facility to provide retraining and job placement services to employees of such contractor.
(b) Closure report
Upon the permanent cessation of production operations at a Department of Energy defense nuclear facility, the Secretary of Energy shall submit to Congress a report containing—
(1) a complete survey of environmental problems at the facility;
(2) budget quality data indicating the cost of defense environmental cleanup activities at the facility; and
(3) a discussion of the proposed cleanup schedule.
(
Editorial Notes
Codification
Section was formerly classified to
Prior Provisions
A prior section 2611,
Amendments
2013—Subsec. (a).
Subsec. (b)(2).
2003—
Statutory Notes and Related Subsidiaries
Defense Site Acceleration Completion
"(a)
"(1) does not require permanent isolation in a deep geologic repository for spent fuel or high-level radioactive waste;
"(2) has had highly radioactive radionuclides removed to the maximum extent practical; and
"(3)(A) does not exceed concentration limits for Class C low-level waste as set out in section 61.55 of title 10, Code of Federal Regulations, and will be disposed of—
"(i) in compliance with the performance objectives set out in subpart C of part 61 of title 10, Code of Federal Regulations; and
"(ii) pursuant to a State-approved closure plan or State-issued permit, authority for the approval or issuance of which is conferred on the State outside of this section; or
"(B) exceeds concentration limits for Class C low-level waste as set out in section 61.55 of title 10, Code of Federal Regulations, but will be disposed of—
"(i) in compliance with the performance objectives set out in subpart C of part 61 of title 10, Code of Federal Regulations;
"(ii) pursuant to a State-approved closure plan or State-issued permit, authority for the approval or issuance of which is conferred on the State outside of this section; and
"(iii) pursuant to plans developed by the Secretary in consultation with the Commission.
"(b)
"(2) If the Commission considers any disposal actions taken by the Department of Energy pursuant to those subparagraphs to be not in compliance with those performance objectives, the Commission shall, as soon as practicable after discovery of the noncompliant conditions, inform the Department of Energy, the covered State, and the following congressional committees:
"(A) The Committee on Armed Services, the Committee on Energy and Commerce, and the Committee on Appropriations of the House of Representatives.
"(B) The Committee on Armed Services, the Committee on Energy and Natural Resources, the Committee on Environment and Public Works, and the Committee on Appropriations of the Senate.
"(3) For fiscal year 2005, the Secretary shall, from amounts available for defense site acceleration completion, reimburse the Commission for all expenses, including salaries, that the Commission incurs as a result of performance under subsection (a) and this subsection for fiscal year 2005. The Department of Energy and the Commission may enter into an interagency agreement that specifies the method of reimbursement. Amounts received by the Commission for performance under subsection (a) and this subsection may be retained and used for salaries and expenses associated with those activities, notwithstanding
"(4) For fiscal years after 2005, the Commission shall include in the budget justification materials submitted to Congress in support of the Commission budget for that fiscal year (as submitted with the budget of the President under
"(c)
"(d)
"(1) The State of South Carolina.
"(2) The State of Idaho.
"(e)
"(2) Nothing in this section establishes any precedent or is binding on the State of Washington, the State of Oregon, or any other State not covered by subsection (d) for the management, storage, treatment, and disposition of radioactive and hazardous materials.
"(3) Nothing in this section amends the definition of 'transuranic waste' or regulations for repository disposal of transuranic waste pursuant to the Waste Isolation Pilot Plant Land Withdrawal Act [
"(4) Nothing in this section shall be construed to affect in any way the obligations of the Department of Energy to comply with section 4306A of the Atomic Energy Defense Act (
"(5) Nothing in this section amends the West Valley Demonstration Act [
"(f)
"(1) Any determination made by the Secretary or any other agency action taken by the Secretary pursuant to this section.
"(2) Any failure of the Commission to carry out its responsibilities under subsection (b)."
Sandia National Laboratories
§2603. Plan for deactivation and decommissioning of nonoperational defense nuclear facilities
(a) In general
The Secretary of Energy shall, every four years beginning in 2025, develop and subsequently carry out a plan for the activities of the Department of Energy relating to the deactivation and decommissioning of nonoperational defense nuclear facilities.
(b) Elements
The plan required by subsection (a) shall include the following:
(1) A list of nonoperational defense nuclear facilities, prioritized for deactivation and decommissioning based on the potential to reduce risks to human health, property, or the environment and to maximize cost savings.
(2) An assessment of the life cycle costs of each nonoperational defense nuclear facility during the period beginning on the date on which the plan is submitted under subsection (d) and ending on the earlier of—
(A) the date that is 25 years after the date on which the plan is submitted; or
(B) the estimated date for deactivation and decommissioning of the facility.
(3) An estimate of the cost and time needed to deactivate and decommission each nonoperational defense nuclear facility.
(4) A schedule for when the Office of Environmental Management will accept each nonoperational defense nuclear facility for deactivation and decommissioning.
(5) An estimate of costs that could be avoided by—
(A) accelerating the cleanup of nonoperational defense nuclear facilities; or
(B) other means, such as reusing such facilities for another purpose.
(c) Plan for transfer of responsibility for certain facilities
The Secretary shall, during 2025, develop and subsequently carry out a plan under which the Administrator shall transfer, by March 31, 2029, to the Assistant Secretary for Environmental Management the responsibility for decontaminating and decommissioning facilities of the Administration that the Secretary determines are nonoperational as of September 30, 2024.
(d) Submission to Congress
Not later than March 31, 2025, and every four years thereafter,,1 the Secretary shall submit to the appropriate congressional committees a report that includes—
(1) the plan required by subsection (a);
(2) a description of the deactivation and decommissioning actions expected to be taken during the following fiscal year pursuant to the plan;
(3) in the case of the report submitted during 2025, the plan required by subsection (c); and
(4) a description of the deactivation and decommissioning actions taken at each nonoperational defense nuclear facility during the period following the date on which the previous report required by this section was submitted.
(e) Termination
The requirements of this section shall terminate after the submission to the appropriate congressional committees of the report required by subsection (d) to be submitted not later than March 31, 2033.
(f) Definitions
In this section:
(1) The term "appropriate congressional committees" means—
(A) the congressional defense committees; and
(B) the Committee on Energy and Natural Resources of the Senate and the Committee on Energy and Commerce of the House of Representatives.
(2) The term "life cycle costs", with respect to a facility, means—
(A) the present and future costs of all resources and associated cost elements required to develop, produce, deploy, or sustain the facility; and
(B) the present and future costs to deactivate, decommission, and deconstruct the facility.
(3) The term "nonoperational defense nuclear facility" means a production facility or utilization facility (as those terms are defined in
(
Editorial Notes
Amendments
2022—Subsec. (a).
Subsec. (c).
"(1) are nonoperational as of September 30, 2015; and
"(2) meet the requirements of the Office of Environmental Management for such transfer."
Subsec. (d).
Subsec. (d)(3).
Subsec. (d)(4).
Subsec. (e).