§22903. Project management oversight
(a)
(1) adequate recipient staff organization with well-defined reporting relationships, statements of functional responsibilities, job descriptions, and job qualifications;
(2) a budget covering the project management organization, appropriate consultants, property acquisition, utility relocation, systems demonstration staff, audits, and miscellaneous payments the recipient may be prepared to justify;
(3) a construction schedule for the project;
(4) a document control procedure and recordkeeping system;
(5) a change order procedure that includes a documented, systematic approach to handling the construction change orders;
(6) organizational structures, management skills, and staffing levels required throughout the construction phase;
(7) quality control and quality assurance functions, procedures, and responsibilities for construction, system installation, and integration of system components;
(8) material testing policies and procedures;
(9) internal plan implementation and reporting requirements;
(10) criteria and procedures to be used for testing the operational system or its major components;
(11) periodic updates of the plan, especially related to project budget and project schedule, financing, and ridership estimates; and
(12) the recipient's commitment to submit periodically a project budget and project schedule to the Secretary.