§6285. Life-cycle cost estimates of certain atomic energy defense capital assets

(a) In General.-The Secretary of Energy shall ensure that an independent life-cycle cost estimate under Department of Energy Order 413.3B (relating to program management and project management for the acquisition of capital assets), or a successor order, of each capital asset described in subsection (b) is conducted before the asset achieves critical decision 2 in the acquisition process.

(b) Capital Assets Described.-A capital asset described in this subsection is an atomic energy defense capital asset-

(1) the total project cost of which exceeds $100,000,000; and

(2) the purpose of which is to perform a limited-life, single-purpose mission.


(c) Independent Defined.-For purposes of subsection (a), the term "independent", with respect to a life-cycle cost estimate of a capital asset, means that the life-cycle cost estimate is prepared by an organization independent of the project sponsor, using the same detailed technical and procurement information as the sponsor, to determine if the life-cycle cost estimate of the sponsor is accurate and reasonable.

(Added Pub. L. 119–60, div. C, title XXXI, §3111(a), Dec. 18, 2025, 139 Stat. 1434 .)


Editorial Notes

Prior Provisions

Provisions similar to those in this section were contained in section 2754 of Title 50, War and National Defense, prior to repeal by Pub. L. 119–60, §3111(b)(1).