42 USC 2372: Date of transfer of utilities
Result 1 of 1
   
 
42 USC 2372: Date of transfer of utilities Text contains those laws in effect on November 20, 2024
From Title 42-THE PUBLIC HEALTH AND WELFARECHAPTER 24-DISPOSAL OF ATOMIC ENERGY COMMUNITIESSUBCHAPTER VI-UTILITIES

§2372. Date of transfer of utilities

Transfers of utilities shall be made as soon as possible, but in any event, not later than five years after August 4, 1955, in the case of Oak Ridge and Richland, or, in the case of Los Alamos, not later than June 30, 1998.

(Aug. 4, 1955, ch. 543, ch. 7, §72, 69 Stat. 480 ; Pub. L. 87–719, §20, Sept. 28, 1962, 76 Stat. 666 ; Pub. L. 104–106, div. C, title XXXI, §3161(a), Feb. 10, 1996, 110 Stat. 627 .)


Editorial Notes

Amendments

1996-Pub. L. 104–106 substituted "not later than June 30, 1998" for "not later than five years after the date it is included within this chapter".

1962-Pub. L. 87–719 inserted "in the case of Oak Ridge and Richland, or, in the case of Los Alamos, not later than five years after the date it is included within this chapter" after "August 4, 1955,".