SUBCHAPTER V—PROCUREMENT PROTEST SYSTEM
§3551. Definitions
In this subchapter:
(1) The term "protest" means a written objection by an interested party to any of the following:
(A) A solicitation or other request by a Federal agency for offers for a contract for the procurement of property or services.
(B) The cancellation of such a solicitation or other request.
(C) An award or proposed award of such a contract.
(D) A termination or cancellation of an award of such a contract, if the written objection contains an allegation that the termination or cancellation is based in whole or in part on improprieties concerning the award of the contract.
(E) Conversion of a function that is being performed by Federal employees to private sector performance.
(2) The term "interested party"—
(A) with respect to a contract or a solicitation or other request for offers described in paragraph (1), means an actual or prospective bidder or offeror whose direct economic interest would be affected by the award of the contract or by failure to award the contract; and
(B) with respect to a public-private competition conducted under Office of Management and Budget Circular A–76 with respect to the performance of an activity or function of a Federal agency, or a decision to convert a function performed by Federal employees to private sector performance without a competition under Office of Management and Budget Circular A–76, includes—
(i) any official who is responsible for submitting the agency tender in such competition; and
(ii) any one individual who, for the purpose of representing the Federal employees engaged in the performance of the activity or function for which the public-private competition is conducted in a protest under this subchapter that relates to such public-private competition, has been designated as the agent of the Federal employees by a majority of such employees.
(3) The term "Federal agency" has the meaning given such term by
(Added
Editorial Notes
Amendments
2009—Par. (1)(E).
Par. (2)(B)(i).
2008—Par. (2).
"(A) with respect to a contract or a solicitation or other request for offers described in paragraph (1), means an actual or prospective bidder or offeror whose direct economic interest would be affected by the award of the contract or by failure to award the contract; and
"(B) with respect to a public-private competition conducted under Office of Management and Budget Circular A–76 regarding performance of an activity or function of a Federal agency, or a decision to convert a function performed by Federal employees to private sector performance without a competition under OMB Circular A–76, includes—
"(i) any official who submitted the agency tender in such competition; and
"(ii) any one person who, for the purpose of representing them in a protest under this subchapter that relates to such competition, has been designated as their agent by a majority of the employees of such Federal agency who are engaged in the performance of such activity or function."
2007—Par. (2).
"(2)(A) The term 'interested party', with respect to a contract or a solicitation or other request for offers described in paragraph (1), means an actual or prospective bidder or offeror whose direct economic interest would be affected by the award of the contract or by failure to award the contract.
"(B) The term includes the official responsible for submitting the Federal agency tender in a public-private competition conducted under Office of Management and Budget Circular A–76 regarding an activity or function of a Federal agency performed by more than 65 full-time equivalent employees of the Federal agency."
2004—Par. (2).
2002—Par. (3).
1996—
Par. (2).
1994—Par. (1).
Par. (2).
Par. (3).
1985—Par. (1).
Statutory Notes and Related Subsidiaries
Effective Date of 2009 Amendment
"(1) to any protest or civil action that relates to a public-private competition conducted after the date of the enactment of this Act [Oct. 28, 2009] under Office of Management and Budget Circular A–76, or any successor circular; and
"(2) to a decision made after the date of the enactment of this Act to convert a function performed by Federal employees to private sector performance without a competition under Office of Management and Budget Circular A–76."
Effective Date of 2008 Amendment
Par. (2)(B) of this section, as added by
Effective Date of 2007 Amendment
Paragraph (2)(B) of this section applicable to protests and civil actions that challenge final selections of sources of performance of an activity or function of a Federal agency that are made pursuant to studies initiated under Office of Management and Budget Circular A–76 on or after Jan. 1, 2004; and to any other protests and civil actions that relate to public-private competitions initiated under Office of Management and Budget Circular A–76, or a decision to convert a function performed by Federal employees to private sector performance without a competition under Office of Management and Budget Circular A–76, on or after Dec. 26, 2007, see section 739(c)(3) of
Amendment by
Effective Date of 2004 Amendment
Effective Date of 1996 Amendment
For effective date and applicability of amendment by
Effective Date of 1994 Amendment
For effective date and applicability of amendment by
Effective Date
Section applicable with respect to any protest filed after Jan. 14, 1985, see section 2751(b) of
Construction of 2004 Amendment
§3552. Protests by interested parties concerning procurement actions
(a) A protest concerning an alleged violation of a procurement statute or regulation shall be decided by the Comptroller General if filed in accordance with this subchapter.
(b)(1) In the case of an agency tender official who is an interested party under
(2) The determination of an agency tender official under paragraph (1) whether or not to file a protest is not subject to administrative or judicial review. An agency tender official shall provide written notification to Congress whenever the official makes a determination under paragraph (1) that there is no reasonable basis for a protest.
(Added
Editorial Notes
Amendments
2004—
1996—
1994—
Statutory Notes and Related Subsidiaries
Effective Date of 2004 Amendment
Amendment by
Effective Date of 1996 Amendment
Amendment by
Effective Date of 1994 Amendment
For effective date and applicability of amendment by
Effective Date
Section applicable with respect to any protest filed after Jan. 14, 1985, see section 2751(b) of
Construction of 2004 Amendment
Amendment by
§3553. Review of protests; effect on contracts pending decision
(a) Under procedures prescribed under
(b)(1) Within one day after the receipt of a protest, the Comptroller General shall notify the Federal agency involved of the protest.
(2) Except as provided in paragraph (3) of this subsection, a Federal agency receiving a notice of a protested procurement under paragraph (1) of this subsection shall submit to the Comptroller General a complete report (including all relevant documents) on the protested procurement—
(A) within 30 days after the date of the agency's receipt of that notice;
(B) if the Comptroller General, upon a showing by the Federal agency, determines (and states the reasons in writing) that the specific circumstances of the protest require a longer period, within the longer period determined by the Comptroller General; or
(C) in a case determined by the Comptroller General to be suitable for the express option under
(3) A Federal agency need not submit a report to the Comptroller General pursuant to paragraph (2) of this subsection if the agency is sooner notified by the Comptroller General that the protest concerned has been dismissed under
(c)(1) Except as provided in paragraph (2) of this subsection, a contract may not be awarded in any procurement after the Federal agency has received notice of a protest with respect to such procurement from the Comptroller General and while the protest is pending.
(2) The head of the procuring activity responsible for award of a contract may authorize the award of the contract (notwithstanding a protest of which the Federal agency has notice under this section)—
(A) upon a written finding that urgent and compelling circumstances which significantly affect interests of the United States will not permit waiting for the decision of the Comptroller General under this subchapter; and
(B) after the Comptroller General is advised of that finding.
(3) A finding may not be made under paragraph (2)(A) of this subsection unless the award of the contract is otherwise likely to occur within 30 days after the making of such finding.
(d)(1) A contractor awarded a Federal agency contract may, during the period described in paragraph (4), begin performance of the contract and engage in any related activities that result in obligations being incurred by the United States under the contract unless the contracting officer responsible for the award of the contract withholds authorization to proceed with performance of the contract.
(2) The contracting officer may withhold an authorization to proceed with performance of the contract during the period described in paragraph (4) if the contracting officer determines in writing that—
(A) a protest is likely to be filed; and
(B) the immediate performance of the contract is not in the best interests of the United States.
(3)(A) If the Federal agency awarding the contract receives notice of a protest in accordance with this section during the period described in paragraph (4)—
(i) the contracting officer may not authorize performance of the contract to begin while the protest is pending; or
(ii) if authorization for contract performance to proceed was not withheld in accordance with paragraph (2) before receipt of the notice, the contracting officer shall immediately direct the contractor to cease performance under the contract and to suspend any related activities that may result in additional obligations being incurred by the United States under that contract.
(B) Performance and related activities suspended pursuant to subparagraph (A)(ii) by reason of a protest may not be resumed while the protest is pending.
(C) The head of the procuring activity may authorize the performance of the contract (notwithstanding a protest of which the Federal agency has notice under this section)—
(i) upon a written finding that—
(I) performance of the contract is in the best interests of the United States; or
(II) urgent and compelling circumstances that significantly affect interests of the United States will not permit waiting for the decision of the Comptroller General concerning the protest; and
(ii) after the Comptroller General is notified of that finding.
(4)(A) The period referred to in paragraphs (2) and (3)(A), with respect to a contract, is the period beginning on the date of the contract award and ending on the later of—
(i) the date that is 10 days after the date of the contract award; or
(ii) the date that is 5 days after the debriefing date offered to an unsuccessful offeror for any debriefing that is requested and, when requested, is required.
(B) For procurements conducted by any component of the Department of Defense, the 5-day period described in subparagraph (A)(ii) does not commence until the day the Government delivers to a disappointed offeror the written responses to any questions submitted pursuant to
(e) The authority of the head of the procuring activity to make findings and to authorize the award and performance of contracts under subsections (c) and (d) of this section may not be delegated.
(f)(1) Within such deadlines as the Comptroller General prescribes, upon request each Federal agency shall provide to an interested party any document relevant to a protested procurement action (including the report required by subsection (b)(2) of this section) that would not give that party a competitive advantage and that the party is otherwise authorized by law to receive.
(2)(A) The Comptroller General may issue protective orders which establish terms, conditions, and restrictions for the provision of any document to a party under paragraph (1), that prohibit or restrict the disclosure by the party of information described in subparagraph (B) that is contained in such a document.
(B) Information referred to in subparagraph (A) is procurement sensitive information, trade secrets, or other proprietary or confidential research, development, or commercial information.
(C) A protective order under this paragraph shall not be considered to authorize the withholding of any document or information from Congress or an executive agency.
(g) If an interested party files a protest in connection with a public-private competition described in
(Added
Editorial Notes
Amendments
2021—Subsec. (d)(4)(B).
2017—Subsec. (d)(4).
2004—Subsec. (g).
1996—Subsec. (b)(2)(A).
Subsec. (b)(3).
1994—Subsec. (b)(1).
Subsec. (b)(2)(A).
Subsec. (b)(2)(C).
Subsec. (c)(3).
Subsec. (d).
"(d)(1) If a Federal agency receives notice of a protest under this section after the contract has been awarded but within 10 days of the date of the contract award, the Federal agency (except as provided under paragraph (2)) shall, upon receipt of that notice, immediately direct the contractor to cease performance under the contract and to suspend any related activities that may result in additional obligations being incurred by the United States under that contract. Performance of the contract may not be resumed while the protest is pending.
"(2) The head of the procuring activity responsible for award of a contract may authorize the performance of the contract (notwithstanding a protest of which the Federal agency has notice under this section)—
"(A) upon a written finding—
"(i) that performance of the contract is in the best interests of the United States; or
"(ii) that urgent and compelling circumstances that significantly affect interests of the United States will not permit waiting for the decision of the Comptroller General concerning the protest; and
"(B) after the Comptroller General is notified of that finding."
Subsec. (f).
Statutory Notes and Related Subsidiaries
Effective Date of 2004 Amendment
Amendment by
Effective Date of 1996 Amendment
For effective date and applicability of amendment by section 4321(d)(2) of
Amendment by section 5501(1) of
Effective Date of 1994 Amendment
For effective date and applicability of amendment by
Effective Date
Section applicable with respect to any protest filed after Jan. 14, 1985, see section 2751(b) of
Construction of 2004 Amendment
Amendment by
§3554. Decisions on protests
(a)(1) To the maximum extent practicable, the Comptroller General shall provide for the inexpensive and expeditious resolution of protests under this subchapter. Except as provided under paragraph (2) of this subsection, the Comptroller General shall issue a final decision concerning a protest within 100 days after the date the protest is submitted to the Comptroller General.
(2) The Comptroller General shall, by regulation prescribed pursuant to
(3) An amendment to a protest that adds a new ground of protest, if timely made, should be resolved, to the maximum extent practicable, within the time limit established under paragraph (1) of this subsection for final decision of the initial protest. If an amended protest cannot be resolved within such time limit, the Comptroller General may resolve the amended protest through the express option under paragraph (2) of this subsection.
(4) The Comptroller General may dismiss a protest that the Comptroller General determines is frivolous or which, on its face, does not state a valid basis for protest.
(b)(1) With respect to a solicitation for a contract, or a proposed award or the award of a contract, protested under this subchapter, the Comptroller General may determine whether the solicitation, proposed award, or award complies with statute and regulation. If the Comptroller General determines that the solicitation, proposed award, or award does not comply with a statute or regulation, the Comptroller General shall recommend that the Federal agency—
(A) refrain from exercising any of its options under the contract;
(B) recompete the contract immediately;
(C) cancel the solicitation issued pursuant to the public-private competition conducted under Office of Management and Budget Circular A–76 or any successor circular;
(D) issue a new solicitation;
(E) terminate the contract;
(F) award a contract consistent with the requirements of such statute and regulation;
(G) implement any combination of recommendations under clauses (A), (B), (C), (D), (E), and (F); or
(H) implement such other recommendations as the Comptroller General determines to be necessary in order to promote compliance with procurement statutes and regulations.
(2) If the head of the procuring activity responsible for a contract makes a finding under
(3) If the Federal agency fails to implement fully the recommendations of the Comptroller General under this subsection with respect to a solicitation for a contract or an award or proposed award of a contract within 60 days after receiving the recommendations, the head of the procuring activity responsible for that contract shall report such failure to the Comptroller General not later than 5 days after the end of such 60-day period.
(c)(1) If the Comptroller General determines that a solicitation for a contract or a proposed award or the award of a contract does not comply with a statute or regulation, the Comptroller General may recommend that the Federal agency conducting the procurement pay to an appropriate interested party the costs of—
(A) filing and pursuing the protest, including reasonable attorneys' fees and consultant and expert witness fees; and
(B) bid and proposal preparation.
(2) No party (other than a small business concern (within the meaning of section 3(a) of the Small Business Act)) may be paid, pursuant to a recommendation made under the authority of paragraph (1)—
(A) costs for consultant and expert witness fees that exceed the highest rate of compensation for expert witnesses paid by the Federal Government; or
(B) costs for attorneys' fees that exceed $150 per hour unless the agency determines, based on the recommendation of the Comptroller General on a case by case basis, that an increase in the cost of living or a special factor, such as the limited availability of qualified attorneys for the proceedings involved, justifies a higher fee.
(3) If the Comptroller General recommends under paragraph (1) that a Federal agency pay costs to an interested party, the Federal agency shall—
(A) pay the costs promptly; or
(B) if the Federal agency does not make such payment, promptly report to the Comptroller General the reasons for the failure to follow the Comptroller General's recommendation.
(4) If the Comptroller General recommends under paragraph (1) that a Federal agency pay costs to an interested party, the Federal agency and the interested party shall attempt to reach an agreement on the amount of the costs to be paid. If the Federal agency and the interested party are unable to agree on the amount to be paid, the Comptroller General may, upon the request of the interested party, recommend to the Federal agency the amount of the costs that the Federal agency should pay.
(d) Each decision of the Comptroller General under this subchapter shall be signed by the Comptroller General or a designee for that purpose. A copy of the decision shall be made available to the interested parties, the head of the procuring activity responsible for the solicitation, proposed award, or award of the contract, and the senior procurement executive of the Federal agency involved.
(e)(1) The Comptroller General shall report promptly to the Committee on Governmental Affairs and the Committee on Appropriations of the Senate and to the Committee on Government Reform and Oversight and the Committee on Appropriations of the House of Representatives any case in which a Federal agency fails to implement fully a recommendation of the Comptroller General under subsection (b) or (c). The report shall include—
(A) a comprehensive review of the pertinent procurement, including the circumstances of the failure of the Federal agency to implement a recommendation of the Comptroller General; and
(B) a recommendation regarding whether, in order to correct an inequity or to preserve the integrity of the procurement process, the Congress should consider—
(i) private relief legislation;
(ii) legislative rescission or cancellation of funds;
(iii) further investigation by Congress; or
(iv) other action.
(2) Not later than January 31 of each year, the Comptroller General shall transmit to the Congress a report containing a summary of each instance in which a Federal agency did not fully implement a recommendation of the Comptroller General under subsection (b) or (c) during the preceding year. The report shall also describe each instance in which a final decision in a protest was not rendered within 100 days after the date the protest is submitted to the Comptroller General. The report shall also include a summary of the most prevalent grounds for sustaining protests during such preceding year.
(Added
Editorial Notes
References in Text
Section 3(a) of the Small Business Act, referred to in subsec. (c)(2), is classified to
Amendments
2013—Subsec. (e)(2).
2009—Subsec. (b)(1)(C) to (H).
1996—Subsec. (a)(1).
Subsec. (b)(2).
Subsec. (e)(1).
Subsec. (e)(2).
1994—Subsec. (a)(1).
Subsec. (a)(2).
Subsec. (a)(3), (4).
Subsec. (b)(3).
Subsec. (c).
"(c)(1) If the Comptroller General determines that a solicitation for a contract or a proposed award or the award of a contract does not comply with a statute or regulation, the Comptroller General may declare an appropriate interested party to be entitled to the costs of—
"(A) filing and pursuing the protest, including reasonable attorneys' fees; and
"(B) bid and proposal preparation.
"(2) Monetary awards to which a party is declared to be entitled under paragraph (1) of this subsection shall be paid promptly by the Federal agency concerned out of funds available to or for the use of the Federal agency for the procurement of property and services."
Subsec. (e).
"(e)(1) The head of the procuring activity responsible for the solicitation, proposed award, or award of the contract shall report to the Comptroller General, if the Federal agency has not fully implemented those recommendations within 60 days of receipt of the Comptroller General's recommendations under subsection (b) of this section.
"(2) Not later than January 31 of each year, the Comptroller General shall transmit to Congress a report describing each instance in which a Federal agency did not fully implement the Comptroller General's recommendations during the preceding fiscal year."
1988—Subsec. (a)(1).
Statutory Notes and Related Subsidiaries
Change of Name
Committee on Governmental Affairs of Senate changed to Committee on Homeland Security and Governmental Affairs of Senate, effective Jan. 4, 2005, by Senate Resolution No. 445, One Hundred Eighth Congress, Oct. 9, 2004.
Committee on Government Reform and Oversight of House of Representatives changed to Committee on Government Reform of House of Representatives by House Resolution No. 5, One Hundred Sixth Congress, Jan. 6, 1999. Committee on Government Reform of House of Representatives changed to Committee on Oversight and Government Reform of House of Representatives by House Resolution No. 6, One Hundred Tenth Congress, Jan. 5, 2007. Committee on Oversight and Government Reform of House of Representatives changed to Committee on Oversight and Reform of House of Representatives by House Resolution No. 6, One Hundred Sixteenth Congress, Jan. 9, 2019. Committee on Oversight and Reform of House of Representatives changed to Committee on Oversight and Accountability of House of Representatives by House Resolution No. 5, One Hundred Eighteenth Congress, Jan. 9, 2023.
Effective Date of 2009 Amendment
Amendment by
Effective Date of 1996 Amendment
For effective date and applicability of amendment by section 4321(d)(3) of
Amendment by section 5501(2) of
Effective Date of 1994 Amendment
For effective date and applicability of amendment by
Effective Date
Section applicable with respect to any protest filed after Jan. 14, 1985, see section 2751(b) of
Inclusion of Information on Common Grounds for Sustaining Bid Protests in Annual Government Accountability Office Reports to Congress
Prompt Payment of Costs Under Prior Law
§3555. Regulations; authority of Comptroller General to verify assertions
(a) The Comptroller General shall prescribe such procedures as may be necessary to the expeditious decision of protests under this subchapter, including procedures for accelerated resolution of protests under the express option authorized by
(b) The procedures shall provide that, in the computation of any period described in this subchapter—
(1) the day of the act, event, or default from which the designated period of time begins to run not be included; and
(2) the last day after such act, event, or default be included, unless—
(A) such last day is a Saturday, a Sunday, or a legal holiday; or
(B) in the case of a filing of a paper at the Government Accountability Office or a Federal agency, such last day is a day on which weather or other conditions cause the closing of the Government Accountability Office or Federal agency, in which event the next day that is not a Saturday, Sunday, or legal holiday shall be included.
(c)
(1)
(A) a person filing a protest under this subchapter may file the protest through electronic means; and
(B) all documents and information required with respect to the protest may be disseminated and made available to the parties to the protest through electronic means.
(2)
(A)
(B)
(3)
(A)
(B)
(d) The Comptroller General may use any authority available under
(Added
Editorial Notes
Amendments
2014—Subsec. (c).
2004—Subsec. (b)(2)(B).
1994—Subsec. (a).
Subsecs. (b) to (d).
Statutory Notes and Related Subsidiaries
Effective Date of 1994 Amendment
For effective date and applicability of amendment by
Effective Date
Section applicable with respect to any protest filed after Jan. 14, 1985, see section 2751(b) of
§3556. Nonexclusivity of remedies; matters included in agency record
This subchapter does not give the Comptroller General exclusive jurisdiction over protests, and nothing contained in this subchapter shall affect the right of any interested party to file a protest with the contracting agency or to file an action in the United States Court of Federal Claims. In any such action based on a procurement or proposed procurement with respect to which a protest has been filed under this subchapter, the reports required by
(Added
Editorial Notes
Amendments
1996—
1992—
Statutory Notes and Related Subsidiaries
Effective Date of 1996 Amendment
Amendment by
Effective Date of 1992 Amendment
Amendment by
Effective Date
Section applicable with respect to any protest filed after Jan. 14, 1985, see section 2751(b) of
Nonexclusivity of GAO Remedies
§3557. Expedited action in protests of public-private competitions
For any protest of a public-private competition conducted under Office of Management and Budget Circular A–76 with respect to the performance of an activity or function of a Federal agency, the Comptroller General shall administer the provisions of this subchapter in the manner best suited for expediting the final resolution of the protest and the final action in the public-private competition.
(Added
Editorial Notes
Codification
Another section 3557, added
Amendments
2008—